2026 Detours

Blair County


  • Scope: Structure replacement​
  • Traffic Control: Detour (8.1 miles)​
  • Construction Timeframe: June – July 2026​
  • Detour Implementation Date: June 2, 2026​ 
  • Anticipated Date Detour to be Lifted: July 7, 2026​
  • Contractor: Glenn O. Hawbaker, Inc.​
  • Current Contract: $5,136,136​ (Bid with Route 3013 Blair Gap Run Bridge​)

 

View Route 3013 Dry Run Bridge Map (PDF).

  • Scope: Resurfacing and Slide Stabilization​
  • Traffic Control: Detour (23.5 miles)​
  • Construction Timeframe: March 2026 to July 2027
  • Detour Implementation Date: March 24, 2026
  • Anticipated Date Detour to be Lifted: August 2026
  • Contractor: New Enterprise Stone & Lime, New Enterprise, Pa.
  • Current Contract: $8,405,252.50

 

View Route 453 Tyrone Snyder Twp Detour and Project Map (PDF).

Visit the Route 453 Tyrone Snyder Twp Resurfacing and Slide Stabilization Project Page

Bedford County


  • Scope: Pavement Resurfacing  ​
  • Traffic Control: Detour (2.5 miles)​
  • Construction Timeframe: April to October 2026​
  • Detour Implementation Date: April 21, 2026​ 
  • Anticipated Date Detour to be Lifted: Four (4) to seven (7) days per ramp closure. Only one ramp will be closed at a time. 
  • Detour Route:  Continue on U.S. 30 to U.S. 220 South Cumberland exit-ramp, to the U.S. 220 South Bedford exit, to Route 4010 (Pitt Street) and back to the U.S. 220 North, I-99 North and Altoona ramp.   
  • Contractor: New Enterprise Stone & Lime Co., Inc. New Enterprise, Pa.
  • Current Contract: $6,059,067 

 

View US 30 Ramp to US 220 North I99 North Altoona Detour  (PDF).

 

 

 

 





Cambria County

​Route 3104 Mt. Airy Drive Bridge 

  • Scope: Bridege Rehabilitation ​
  • Traffic Control: Detour (2.9 miles)​
  • Construction Timeframe: March to October 2026​
  • Detour Implementation Date: March 30, 2026​ 
  • Anticipated Date Detour to be Lifted: October 2026
  • Contractor: J.F.Shea Construction, Inc., Mount Pleasant, Pa.
  • Current Contract: $2,257,170 

 

View Route 3104 Mt Airy Drive Bridge Rehab Detour Map (PDF)

View Route 3104 Mt Airy Drive Bridge Rehabe Detour and 2 US 219 Overnight Detours Map (PDF)

 

 

 

 





Route 160 (Forest Hills Drive) over South Fork branch of Little Conemaugh River Bridge Detour & T-330 (Plummer Road) Detour

  • Scope: Two Bridge Superstructure Replacements
  • Traffic Control: Detour of Route 160 (7.9 miles)​ and weekend detours of T-330 Plummer Road (4.6 miles)
  • Construction Timeframe: June – September 2026​
  • Anticipated Detour Implementation Date: June 9, 2026​
  • Anticipated Date Detour to be Lifted: August 7, 2026
  • Route 160 Detour Route: 1. Route 869 (Locust Street), Route 160 (Mill Road, Fairview Avenue, Springside Avenue). Route 53 (Portage Street, Railroad Street), U.S. 219
  • T-330 Detour Route: Route 160 (Mill Road), Betz Road, Black Road, T-330 (Plummer Road).
  • Contractor: Merlo, Inc.​
  • Current Contract: $ 3,453,000  

View Route 160 Detour and T-330 Detour Maps (PDF)

Route 4017 (Ridge Avenue) Over Chest Creek Bridge

  • Scope:  Superstructure Replacement​
  • Traffic Control: Detour (7.5 miles)
  • Construction Timeframe: May – August 2026​
  • Anticipated Detour Implementation Date: June 1, 2026​
  • Anticipated Date Detour to be Lifted: August 3, 2026​
  • Detour Route: Route 4017 (Ridge Avenue/St. Lawrence Road), Route 4024 (Thomas Mill Road), Route 36 (Main Street/Railroad Avenue)
  • Contractor: Kukurin Contracting, Inc.​
  • Current Contract: $ 1,284,482

View Route 4017 (Ridge Avenue) over Chest Creek Bridge Detour Map (PDF)

Route 756 Lambert Avenue to Industrial Park Road 

  • Scope: Resurfacing (2.4 miles), drainage upgrades, sight distance improvements, turn lanes, traffic signal upgrades, and pedestrian accommodations
  • Traffic Control: Daylight and nighttime flagging, US 219 ramps and Route 756 nighttime detours, various sideroad detours during certain construction phases
  • Construction Timeframe: April 2026 – October 2027
  • Contractor: A. Liberoni, Inc.
  • Current Contract: $ 9,473,117

View Route 756 Lambert Ave. to Industrial Park Road Detour Maps (PDF)

Route 160 Conemaugh River Culvert

  • Scope: Bridge Replacement
  • Traffic Control: Detour (12.1 miles)
  • Construction Timeframe: March - July 2027
  • Anticipated Detour Implementation Date: June 6, 2027
  • Anticipated Date Detour to be Lifted: June 23, 2027
  • Contractor: Cottle’s Asphalt Maintenance, Inc.
  • Current Contract: $ 1,358,370

View Route 160 Conemaugh River Culvert Detour Map (PDF)

Fulton County

  • Scope: Bridge Replacement (T-313 over Tributary to Sawmill Hollow Run), Single-Cell Precast Concrete Box Culvert, Rip Rap Protection, Minor Approach Roadway Work
  • Traffic Control: Detour – 9.69 Miles
  • Detour Route: Route 301 (Hill Road) detour uses Route 484 (Buck Valley Road) and Route 3003 (Stoneybreak Road)
  • Anticipated Detour Timeframe: August – September 2026
  • Construction Timeframe: April 2026 – November 2026
  • Contractor: George S. Hann & Sons, Inc.
  • Current Contract: $1,017,000

 

View T-313 Sawmill Hollow Route 301 (Hill Road) Detour Map (PDF).


  • Scope: Bridge Replacement over McKees Run, guide rail updates, approach roadway improvements
  • Traffic Control: Detour – 4.63 Miles 
  • Detour Route: T-330 (Zachs Ridge Road) detour will use Route 731 (Fairview Road/McKees Gap Road).
  • Anticipated Detour Timeframe: August – September 2026
  • Construction Timeframe: April 2026 – November 2026​
  • Contractor: Wen-Brooke Contracting Inc. 
  • Current Contract: $776,084

View T-330 (Zachs Ridge Road) Detour Map (PDF) 

Huntingdon County

Route 2004 (Meadow Gap Road) Lick Run Bridge

  • Scope: Structure Replacement​​ w/ Precast Concrete Box Culvert
  • Traffic Control: Detour (9.4 miles)​
  • Construction Timeframe: June – September 2026​
  • Detour Implementation Date: Early June 2026 (31-day maximum duration)​
  • Anticipated Date Detour to be Lifted: By Mid-August 2026​
  • Detour Route: Route 2005 (Elliots Run Road), Route 475 (Maddensville Pike), Route 2023 (Grissinger Road/Mt Carmel Road), Route 2004 (Meadow Gap Road)
  • Contractor: Wen-Brooke Contracting Inc.
  • Current Contract: $802,213

 

View Route 2004 (Meadow Gap Road) Lick Run Bridge Detour Map (PDF).


Route 994 (Old Plank Road) Tributary to Great Trough Creek Bridge 

  • Scope: Structure Replacement​ w/ Precast Concrete Box Culvert
  • Traffic Control: Detour (16.1 miles)​
  • Construction Timeframe: June – August 2026​
  • Detour Implementation Date: Early June 2026 (11-day maximum duration)​
  • Anticipated Date Detour to be Lifted: By Late August 2026
  • Detour Route: Route 994 (Old Plank Road), Route 3019 (Logging Road), Route 913 (North Main Street/Railroad Avenue/Main Street/Barnett Road/), Route 3001 (Little Valley Road)
  • Contractor: Cottle’s Asphalt Maintenance, Inc.​
  • Current Contract: $788,143

View Route 994 Old Plank Road Tributary to Great Trough Creek Bridge Detour Map (PDF) 

Somerset County


  • Scope: Bridege Rehabilitation ​
  • Traffic Control: Detour (4.7 miles)​
  • Construction Timeframe: April to November 2026
  • Detour Implementation Date: April 6, 2026 
  • Anticipated Date Detour to be Lifted: August 2026
  • Contractor: New Enterprise Stone & Lime, New Enterprise, Pa.
  • Current Contract: $24,600,000

 

View T-685 Miller Road Bridge on US 219 Somerset Co Detour (PDF).

 

 

 

 





Route 4041 Stoney Creek Tributary Bridge

  • Scope: Bridge Replacement​ on Route 4041 (Soap Hollow Road)
  • Traffic Control: Detour (5.6 miles)
  • Construction Timeframe: May – August 2026
  • Anticipated Detour Implementation Date: June 4, 2026​
  • Anticipated Date Detour to be Lifted: August 20, 2026
  • Detour Route: Route 4041 (Soap Hollow Road), Route 4043 (West Campus Avenue/Ham Road), Route 403 (Tire Hill Road)  ​
  • Contractor: Merlo, Inc.
  • Current Contract: $ 1,027,000

View Route 4041 Stoney Creek Tributary Bridge Detour Map (PDF)

Route 7209 T-364 (Jimtown Road) Gardner Bridge over Laurel Creek

  • Scope: Bridge Replacement
  • Location: Jefferson Township
  • Traffic Control: Detour (4.2 miles)
  • Construction Timeframe: April – November 2026​
  • Anticipated Detour Implementation Date: Bridge currently closed
  • Anticipated Date Detour to be Lifted: October 28, 2026
  • Detour Route: T-364 (Jimtown Road), Route 3037 (Trent Road), Route 31 (Glades Pike) 
  • Contractor: Plum Contracting, Inc.
  • Current Contract: $ 1,284,360

View Route 7209 T-364 Jimtown Road Gardner Bridge Detour

Route 2001 (Oak Dale Road) Laurel Creek Bridge

  • Scope: Bridge Replacement  
  • Traffic Control: Detour (7.5 miles), 32-day duration​
  • Construction Timeframe: July – August 2026​
  • Anticipated Detour Implementation Date: July 13, 2026​
  • Anticipated Date Detour to be Lifted: August 12, 2026
  • Detour Route: Route 2001 (Oak Dale Road), Route 669 (Springs Road), Route 2003 (St Paul Road)
  • Contractor: C. H. & D. Enterprises Inc.
  • Current Contract: $ 1,359,749

View Route 2001 Laurel Creek Bridge Detour Map (PDF)

Route 1021 (School Road) Miller Run Bridge

  • Scope: Bridge Replacement​
  • Traffic Control: Detour (10.3 miles) ​
  • Construction Timeframe: July – September 2026
  • Anticipated Detour Implementation Date: July 28, 2026​
  • Anticipated Date Detour to be Lifted: September 4, 2026​
  • Detour Route: Route 1021 (School Road/Ridge Road), Route 160 (Rock Cut Road), U.S.30 (Lincoln Highway) 
  • Contractor: Pugliano Construction Co., Inc.
  • Current Contract: $ 789,994

 

View Route 1021 School Road Miller Run Bridge Detour Map (PDF)

Route 3007 (Humbert Road) Red Run Bridge

  • Scope: Bridge Replacement
  • Traffic Control: Route 3007 Detour (14.1 miles), T-446 Detour (3.5 miles), 41-day duration​
  • Construction Timeframe: August – October 2026​
  • Anticipated Detour Implementation Date: September 8, 2026
  • Anticipated Date Detour to be Lifted: October 16,2026
  • Detour Route: Route 3007 (Humbert Road) Route 281 (Kingwood Road) 
  • Contractor: Pugliano Construction Co., Inc.​
  • Current Contract: $ 967,778

View Route 3007 (Humbert Road) Red Run Bridge Detour Map (PDF)

Route 3029 (Copper Kettle Highway) Middle Creek Bridge

  • Scope: Bridge Replacement
  • Traffic Control: Route 3029 Detour (13.0 miles), T-703 Detour
  • Construction Timeframe: May – October 2026​
  • Anticipated Detour Implementation Date: June 8, 2026​
  • Anticipated Date Detour to be Lifted: October 14, 2026
  • Detour Route: Route 3029 (Copper Kettle Highway),  Route 271 (New Centerville Road), Route 3010 (Indiantown Road), Route 3037 (Trent Road) 
  • Contractor: J. F. Shea Construction, Inc.
  • Current Contract: $ 1,359,749

View Route 3029 (Copper Kettle Highway) Middle Creek Bridge Detour Map (PDF)