2025 Detours

Cambria County


  • Scope: Resurfacing (5.9 miles)
  • Traffic Control: Short-term flagging, local street detour (0.3 miles), and pedestrian detour
  • Construction Timeframe: April - November 2025
  • Anticipated Detour Implementation Date: April 2025
  • Anticipated Date Detour to be Lifted: September 2025
  • Contractor: Quaker Sales Corporation
  • Current Contract: $ 5,199,141

View the U.S. 219 Ditter's Curve Map (PDF).

 

 

 





Somerset County


  • Scope: Paving, the renovation of multiple bridge-structures, and drainage, guide rail and signage upgrades along five (5) miles of U.S. 219 in Somerset County. 
  • Detours: During the Route 4102 (Sechler Road) bridge-structure renovation, a 6.5-mile detour will divert traffic to Route 281 to Route 4026 (Lake Road) to Route 601 (North Center Avenue) to Gilmour Road (T-861).     During the Route 4104 (Critchfield Road / T-626) bridge-structure renovation, a 2.4-mile detour will divert traffic to Route 601 (Penn Avenue) to Route 4004 (Bicycle Road) to Morris Road (T-548).​ During the 9.4-mile Route 8005 ramps interchange a 14-day detour will use Route 601, Route 4055 and Route 281.   
  • Construction Timeframe: August 2024 - October 2026
  • ​Detour Implementation Dates: April 7, 2025 for appox. 30 days
  • Contractor: New Enterprise Stone & Lime Co., Inc.
  • Current Contract: $25,000,000.00

 

 


  • Scope: Resurfacing, bridge rehabilitations/replacement, drainage and guide rail upgrades (4.7 miles)​
  • Traffic Control: Long-term lane closure w/ short-term ramp detours and side road detours at bridge locations​
  • Construction Timeframe: April 2025 – November 2026​
  • Contractor: New Enterprise Stone & Lime Co., Inc.​
  • Current Contract: $ 24,600,000​

View the Route 8005 Ramp Interchange Map (PDF).

View the Route 8005 Ramp Projects Map (PDF).

View the US 219 to US 30 Bridges Project Map (PDF).

 

 






  • Scope: Bridge Replacement​
  • Traffic Control: Short-Term Flagging & Detour (15.6 miles)​
  • Construction Timeframe: April 2025 – October 2025​
  • Anticipated Detour Implementation Date: July 14, 2025​
  • Anticipated Date Detour to be Lifted: August 14, 2025​
  • Contractor: JVI Group, Inc.​
  • Current Contract: $ 1,102,041  

View the Route 601 Hollsopple Bridge Map (PDF).

 

 

 






  • Scope: Bridge Replacement​
  • Traffic Control: Detour (14.1 miles), 76-day duration​
  • Construction Timeframe: June 2025 – October 2025​
  • Anticipated Detour Implementation Date: June 11, 2025​
  • Anticipated Date Detour to be Lifted: August 25, 2025​
  • Contractor: JVI Group, Inc.​
  • Current Contract: $ 768,827

View the Route 3007 Humbert Road over Smith Run  Bridge Map (PDF).

 

 

 






  • Scope: Bridge Replacement​
  • Traffic Control: Detour (17.2 miles) 17-day duration​
  • Construction Timeframe: May - September 2025​
  • Anticipated Detour Implementation Date: June 10, 2025​
  • Anticipated Date Detour to be Lifted: August 22, 2025​
  • Contractor: Cottle’s Asphalt Maintenance, Inc.​
  • Current Contract: $ 851,400

View the Route 4001 Bakersville Edie Road over Moore Run Bridge Map (PDF).

 

 

 






  • Scope: Bridge Replacement​
  • Traffic Control: Detour (0.8 Miles), Ped. Detour (0.4 Miles) 150-day duration ​
  • Construction Timeframe: June – October 2025​
  • Contractor: A. Merante Contracting Inc.​
  • Current Contract: $1,218,000

View the Route 7422 24th Street over Seese Run Bridge Map (PDF).

 





Planned 2026 Detours

Blair County


  • Scope: Structure replacement​
  • Traffic Control: Detour (8.1 miles)​
  • Construction Timeframe: June – July 2026​
  • Detour Implementation Date: June 2, 2026​ 
  • Anticipated Date Detour to be Lifted: July 7, 2026​
  • Contractor: Glenn O. Hawbaker, Inc.​
  • Current Contract: $5,136,136​ (Bid with Route 3013 Blair Gap Run Bridge​)

 

View Route 3013 Dry Run Bridge Map (PDF).