2026 Detours

Blair County


  • Scope: Structure replacement​
  • Traffic Control: Detour (8.1 miles)​
  • Construction Timeframe: June – July 2026​
  • Detour Implementation Date: June 2, 2026​ 
  • Anticipated Date Detour to be Lifted: July 7, 2026​
  • Contractor: Glenn O. Hawbaker, Inc.​
  • Current Contract: $5,136,136​ (Bid with Route 3013 Blair Gap Run Bridge​)

 

View Route 3013 Dry Run Bridge Map (PDF).

  • Scope: Resurfacing and Slide Stabilization​
  • Traffic Control: Detour (23.5 miles)​
  • Construction Timeframe: March 2026 to July 2027
  • Detour Implementation Date: March 24, 2026
  • Anticipated Date Detour to be Lifted: August 2026
  • Contractor: New Enterprise Stone & Lime, New Enterprise, Pa.
  • Current Contract: $8,405,252.50

 

View Route 453 Tyrone Snyder Twp Detour and Project Map (PDF).

Visit the Route 453 Tyrone Snyder Twp Resurfacing and Slide Stabilization Project Page

Route 3009 (Valley Forge Road) Blair Gap Run Bridge Project
  • Scope: Superstructure Replacement​​ w/ Rolled Bridge Beams & w/ Precast Deck Modules
  • Traffic Control: Detour (10.9 miles)​ 28-day maximum
  • Detour Route: Old U.S. 22, Old U.S. 220 (Dunnings Highway) Route 3003 (Puzzletown Road), and Route 3010 (Poplar Run Road)
  • Construction Timeframe: July – October 2026​
  • Detour Implementation Date: July 20, 2026​
  • Anticipated Date Detour to be Lifted: August 17, 2026​
  • Contractor: HRI, Inc.
  • Current Contract: $903,860

View Route 3009 Blair Gap Run Detour Map (PDF)

Bedford County


  • Scope: Pavement Resurfacing  ​
  • Traffic Control: Detour (2.5 miles)​
  • Construction Timeframe: April to October 2026​
  • Detour Implementation Date: April 21, 2026​ 
  • Anticipated Date Detour to be Lifted: Four (4) to seven (7) days per ramp closure. Only one ramp will be closed at a time. 
  • Detour Route:  Continue on U.S. 30 to U.S. 220 South Cumberland exit-ramp, to the U.S. 220 South Bedford exit, to Route 4010 (Pitt Street) and back to the U.S. 220 North, I-99 North and Altoona ramp.   
  • Contractor: New Enterprise Stone & Lime Co., Inc. New Enterprise, Pa.
  • Current Contract: $6,059,067 

 

View US 30 Ramp to US 220 North I99 North Altoona Detour  (PDF).

 

 

 

 





Cambria County

​Route 3104 Mt. Airy Drive Bridge 

  • Scope: Bridege Rehabilitation ​
  • Traffic Control: Detour (2.9 miles)​
  • Construction Timeframe: March to October 2026​
  • Detour Implementation Date: March 30, 2026​ 
  • Anticipated Date Detour to be Lifted: October 2026
  • Contractor: J.F.Shea Construction, Inc., Mount Pleasant, Pa.
  • Current Contract: $2,257,170 

 

View Route 3104 Mt Airy Drive Bridge Rehab Detour Map (PDF)

View Route 3104 Mt Airy Drive Bridge Rehabe Detour and 2 US 219 Overnight Detours Map (PDF)

 

 

 

 





Route 160 (Forest Hills Drive) over South Fork branch of Little Conemaugh River Bridge Detour & T-330 (Plummer Road) Detour

  • Scope: Two Bridge Superstructure Replacements
  • Traffic Control: Detour of Route 160 (7.9 miles)​ and weekend detours of T-330 Plummer Road (4.6 miles)
  • Construction Timeframe: June – September 2026​
  • Anticipated Detour Implementation Date: June 9, 2026​
  • Anticipated Date Detour to be Lifted: August 7, 2026
  • Route 160 Detour Route: 1. Route 869 (Locust Street), Route 160 (Mill Road, Fairview Avenue, Springside Avenue). Route 53 (Portage Street, Railroad Street), U.S. 219
  • T-330 Detour Route: Route 160 (Mill Road), Betz Road, Black Road, T-330 (Plummer Road).
  • Contractor: Merlo, Inc.​
  • Current Contract: $ 3,453,000  

View Route 160 Detour and T-330 Detour Maps (PDF)

Route 4017 (Ridge Avenue) Over Chest Creek Bridge

  • Scope:  Superstructure Replacement​
  • Traffic Control: Detour (7.5 miles)
  • Construction Timeframe: May – August 2026​
  • Anticipated Detour Implementation Date: June 1, 2026​
  • Anticipated Date Detour to be Lifted: August 3, 2026​
  • Detour Route: Route 4017 (Ridge Avenue/St. Lawrence Road), Route 4024 (Thomas Mill Road), Route 36 (Main Street/Railroad Avenue)
  • Contractor: Kukurin Contracting, Inc.​
  • Current Contract: $ 1,284,482

View Route 4017 (Ridge Avenue) over Chest Creek Bridge Detour Map (PDF)

Route 756 Lambert Avenue to Industrial Park Road 

  • Scope: Resurfacing (2.4 miles), drainage upgrades, sight distance improvements, turn lanes, traffic signal upgrades, and pedestrian accommodations
  • Traffic Control: Daylight and nighttime flagging, US 219 ramps and Route 756 nighttime detours, various sideroad detours during certain construction phases
  • Construction Timeframe: April 2026 – October 2027
  • Contractor: A. Liberoni, Inc.
  • Current Contract: $ 9,473,117

View Route 756 Lambert Ave. to Industrial Park Road Detour Maps (PDF)

Route 160 Conemaugh River Culvert

  • Scope: Bridge Replacement
  • Traffic Control: Detour (12.1 miles)
  • Construction Timeframe: March - July 2027
  • Anticipated Detour Implementation Date: June 6, 2027
  • Anticipated Date Detour to be Lifted: June 23, 2027
  • Contractor: Cottle’s Asphalt Maintenance, Inc.
  • Current Contract: $ 1,358,370

View Route 160 Conemaugh River Culvert Detour Map (PDF)

Fulton County

  • Scope: Bridge Replacement (T-313 over Tributary to Sawmill Hollow Run), Single-Cell Precast Concrete Box Culvert, Rip Rap Protection, Minor Approach Roadway Work
  • Traffic Control: Detour – 9.69 Miles
  • Detour Route: Route 301 (Hill Road) detour uses Route 484 (Buck Valley Road) and Route 3003 (Stoneybreak Road)
  • Anticipated Detour Timeframe: August – September 2026
  • Construction Timeframe: April 2026 – November 2026
  • Contractor: George S. Hann & Sons, Inc.
  • Current Contract: $1,017,000

 

View T-313 Sawmill Hollow Route 301 (Hill Road) Detour Map (PDF).


  • Scope: Bridge Replacement over McKees Run, guide rail updates, approach roadway improvements
  • Traffic Control: Detour – 4.63 Miles 
  • Detour Route: T-330 (Zachs Ridge Road) detour will use Route 731 (Fairview Road/McKees Gap Road).
  • Anticipated Detour Timeframe: August – September 2026
  • Construction Timeframe: April 2026 – November 2026​
  • Contractor: Wen-Brooke Contracting Inc. 
  • Current Contract: $776,084

View T-330 (Zachs Ridge Road) Detour Map (PDF) 

Huntingdon County

Route 2004 (Meadow Gap Road) Lick Run Bridge

  • Scope: Structure Replacement​​ w/ Precast Concrete Box Culvert
  • Traffic Control: Detour (9.4 miles)​
  • Construction Timeframe: June – September 2026​
  • Anticipated Detour Implementation Date: July 7, 2026 (31-day maximum duration)​
  • Anticipated Date Detour to be Lifted: August 6, 2026​
  • Detour Route: Route 2005 (Elliots Run Road), Route 475 (Maddensville Pike), Route 2023 (Grissinger Road/Mt Carmel Road), Route 2004 (Meadow Gap Road)
  • Contractor: Wen-Brooke Contracting Inc.
  • Current Contract: $802,213

 

View Route 2004 (Meadow Gap Road) Lick Run Bridge Detour Map (PDF).


Route 994 (Old Plank Road) Tributary to Great Trough Creek Bridge 

  • Scope: Structure Replacement​ w/ Precast Concrete Box Culvert
  • Traffic Control: Detour (16.1 miles)​
  • Construction Timeframe: June – August 2026​
  • Anticipated Detour Implementation Date: June 16, 2026 (11-day maximum duration)​
  • Anticipated Date Detour to be Lifted: June 26, 2026
  • Detour Route: Route 994 (Old Plank Road), Route 3019 (Logging Road), Route 913 (North Main Street/Railroad Avenue/Main Street/Barnett Road/), Route 3001 (Little Valley Road)
  • Contractor: Cottle’s Asphalt Maintenance, Inc.​
  • Current Contract: $788,143

View Route 994 Old Plank Road Tributary to Great Trough Creek Bridge Detour Map (PDF) 

Somerset County


  • Scope: Bridege Rehabilitation ​
  • Traffic Control: Detour (4.7 miles)​
  • Construction Timeframe: April to November 2026
  • Detour Implementation Date: April 6, 2026 
  • Anticipated Date Detour to be Lifted: August 2026
  • Contractor: New Enterprise Stone & Lime, New Enterprise, Pa.
  • Current Contract: $24,600,000

 

View T-685 Miller Road Bridge on US 219 Somerset Co Detour (PDF).

 

 

 

 





Route 4041 Stoney Creek Tributary Bridge

  • Scope: Bridge Replacement​ on Route 4041 (Soap Hollow Road)
  • Traffic Control: Detour (5.6 miles)
  • Construction Timeframe: May – August 2026
  • Anticipated Detour Implementation Date: June 4, 2026​
  • Anticipated Date Detour to be Lifted: August 20, 2026
  • Detour Route: Route 4041 (Soap Hollow Road), Route 4043 (West Campus Avenue/Ham Road), Route 403 (Tire Hill Road)  ​
  • Contractor: Merlo, Inc.
  • Current Contract: $ 1,027,000

View Route 4041 Stoney Creek Tributary Bridge Detour Map (PDF)

Route 7209 T-364 (Jimtown Road) Gardner Bridge over Laurel Creek

  • Scope: Bridge Replacement
  • Location: Jefferson Township
  • Traffic Control: Detour (4.2 miles)
  • Construction Timeframe: April – November 2026​
  • Anticipated Detour Implementation Date: Bridge currently closed
  • Anticipated Date Detour to be Lifted: October 28, 2026
  • Detour Route: T-364 (Jimtown Road), Route 3037 (Trent Road), Route 31 (Glades Pike) 
  • Contractor: Plum Contracting, Inc.
  • Current Contract: $ 1,284,360

View Route 7209 T-364 Jimtown Road Gardner Bridge Detour

Route 2001 (Oak Dale Road) Laurel Creek Bridge

  • Scope: Bridge Replacement  
  • Traffic Control: Detour (7.5 miles), 32-day duration​
  • Construction Timeframe: July – August 2026​
  • Anticipated Detour Implementation Date: July 13, 2026​
  • Anticipated Date Detour to be Lifted: August 12, 2026
  • Detour Route: Route 2001 (Oak Dale Road), Route 669 (Springs Road), Route 2003 (St Paul Road)
  • Contractor: C. H. & D. Enterprises Inc.
  • Current Contract: $ 1,359,749

View Route 2001 Laurel Creek Bridge Detour Map (PDF)

Route 1021 (School Road) Miller Run Bridge

  • Scope: Bridge Replacement​
  • Traffic Control: Detour (10.3 miles) ​
  • Construction Timeframe: July – September 2026
  • Anticipated Detour Implementation Date: July 28, 2026​
  • Anticipated Date Detour to be Lifted: September 4, 2026​
  • Detour Route: Route 1021 (School Road/Ridge Road), Route 160 (Rock Cut Road), U.S.30 (Lincoln Highway) 
  • Contractor: Pugliano Construction Co., Inc.
  • Current Contract: $ 789,994

 

View Route 1021 School Road Miller Run Bridge Detour Map (PDF)

Route 3007 (Humbert Road) Red Run Bridge

  • Scope: Bridge Replacement
  • Traffic Control: Route 3007 Detour (14.1 miles), T-446 Detour (3.5 miles), 41-day duration​
  • Construction Timeframe: August – October 2026​
  • Anticipated Detour Implementation Date: September 8, 2026
  • Anticipated Date Detour to be Lifted: October 16,2026
  • Detour Route: Route 3007 (Humbert Road) Route 281 (Kingwood Road) 
  • Contractor: Pugliano Construction Co., Inc.​
  • Current Contract: $ 967,778

View Route 3007 (Humbert Road) Red Run Bridge Detour Map (PDF)

Route 3029 (Copper Kettle Highway) Middle Creek Bridge

  • Scope: Bridge Replacement
  • Traffic Control: Route 3029 Detour (13.0 miles), T-703 Detour
  • Construction Timeframe: May – October 2026​
  • Anticipated Detour Implementation Date: June 8, 2026​
  • Anticipated Date Detour to be Lifted: October 21, 2026
  • Detour Route: Route 3029 (Copper Kettle Highway),  Route 271 (New Centerville Road), Route 3010 (Indiantown Road), Route 3037 (Trent Road) 
  • Contractor: J. F. Shea Construction, Inc.
  • Current Contract: $ 1,359,749

View Route 3029 (Copper Kettle Highway) Middle Creek Bridge Detour Map (PDF)

Route 2026 (Berkleys Mill Road) Bridge over Blue Lick Creek, Summit Township

  • Scope: Bridge Replacement
  • Traffic Control: Detour (9.1 miles), 41-day duration​
  • Construction Timeframe: July to September 2026​
  • Anticipated Detour Implementation Date: July 16, 2026​
  • Anticipated Date Detour to be Lifted: August 25, 2026
  • Contractor: Pugliano Construction Co., Inc.
  • Current Contract: $ 834,078

Visit Route 2026 Berkleys Mill Road Detour Map (PDF)