District 8 Projects - Lancaster and York Counties

Norman Wood Bridge Study

Project Status

Step 1 of 4

Development

Next Step:  Design

Public Outreach

Public Meeting

A public meeting featuring a public plans display and project presentation will take place:

Date: Tuesday, November 10, 2026
Time: Public meeting presentation from 5:30 PM to 6:30 PM
Open House from 6:30 PM to 7:30 PM
Location: Robert Fulton Fire Company - 2271 Robert Fulton Hwy, Peach Bottom, PA 17563

Virtual Plans Display

​The virtual plans display will be available online from November 9, 2026 through December 11, 2026. 

Public Comment Period

The public comment period, where the community is encouraged to respond with questions and concerns will be online from November 9, 2026 through December 11, 2026. 

Project Overview

County: Lancaster and York
Municipality: Martic Township and Lower Chanceford Township
State Route: Route 372
Local Name: Norman Wood Bridge
Project Type: Planning
MPMS Number: 115004
Last Updated: October 2026

The Norman Wood Bridge carries Route 372 (Holtwood Road) over the Susquehanna River and two Norfolk Southern Railway Company rail lines, linking Lower Chanceford Township in York County with Martic Township in Lancaster County, Pennsylvania. As the southernmost crossing of the Susquehanna River in Pennsylvania, this bridge serves as a transportation link for regional mobility in lower south-central Pennsylvania, with the nearest vehicular bridge located more than 20 miles north and 14 miles south. The Norman Wood Bridge serves a wide range of travelers, including commuters, trail users/pedestrians, emergency services, agricultural vehicles, and members of Plain Sect communities who regularly use the bridge for horse-drawn buggy travel.

The Norman Wood Bridge was built in 1968, spans 3,510 feet and carries about 5,497 vehicles daily over the Susquehanna River and rail lines. Solutions are needed to address the ongoing degradation of the Norman Wood Bridge's structural components and traffic operational concerns to safely maintain travel for the public.

PennDOT is studying transportation needs in the area and evaluating different options to improve travel and safety. 

Additional Project Information

The Norman Wood Bridge structural degradation has been noted in recent inspection reports. As the bridge is a critical transportation link for regional mobility in south-central Pennsylvania, it is imperative to find a solution that maintains the transportation access across the river. The most cost-effective way to address the ongoing degradation is to determine a long-term solution. The purpose is to provide a safe and efficient crossing of Route 372 over the Susquehanna River and Norfolk Southern Railway Company tracks. Alternatives have been evaluated to develop feasible options to address the current and anticipated deficiencies of the bridge and its approaches. Alternatives under consideration include rehabilitation of the existing structure, superstructure replacement, full replacement on or near the current alignment, and a full replacement off alignment of the existing bridge.

Frequently Asked Questions

The project is currently in the planning/study phase. 

Coordination with the County Metropolitan Planning Organizations will be the next step to obtain acceptance, approval, funding, and advancement of the completed study.  

No. Currently, future phases of the project, including design and construction, are not fully funded. Upon County Metropolitan Planning Organizations’ acceptance and approval, funding allocation efforts will commence. 

No, the project cannot move forward if funding allocations are not secured.  

The Norman Wood Bridge, built in 1968, is being studied to identify long-term solutions that address the bridge’s deteriorating condition to continue to provide safe and reliable access across the Susquehanna River for the surrounding community. 

No. While PennDOT is advancing a rehabilitation program to address the most immediate structural needs of the bridge, continued maintenance alone is not a viable long-term solution. Ongoing deterioration of the structure would require increasingly frequent repairs and associated traffic disruptions over time. A long-term solution is required to address the bridge’s future transportation and structural needs along with maintaining connectivity for the surrounding communities.   

No. Closing the bridge is not a viable long-term solution because it would eliminate an important transportation connection for residents, businesses, and emergency services in the surrounding communities. 

The planning study evaluated a range of alternatives, including rehabilitation of the existing bridge, replacement of the bridge superstructure, full replacement of the bridge on or near the existing alignment, and full replacement on a new alignment. Standard and accelerated construction methods were analyzed for all options.  Each alternative was also evaluated to determine its ability to address the bridge’s long-term transportation and structural needs along with minimizing impacts on community connectivity.  

The methods and options for traffic control and the length of construction durations vary by alternative and range from maintaining traffic on the existing bridge with temporary lane closures to a full bridge closure requiring a detour for the duration of construction. After the study is accepted and approved, the project team will refine its analysis and evaluate traffic control strategies and construction approaches to meet the project's needs while minimizing impacts to the traveling public and surrounding communities. Specific details on traffic control and construction duration for each alternative can be found in the study.

Maintaining access for emergency services is an important consideration in the evaluation of all alternatives. Depending on the selected alternative, temporary traffic control, detours, and other traffic management measures have the potential to affect emergency response routes. Measures such as temporary traffic signal pre-emption may be considered to help reduce impacts during single-lane traffic operations. Among the alternatives evaluated, a full bridge replacement on a new alignment would have the least impact on emergency services because the existing bridge could remain in service during most of the construction period. Coordination with emergency service providers will continue and be refined after the study is accepted and approved.  

School transportation is not anticipated to be significantly affected by any of the alternatives under consideration. The Susquehanna River generally serves as the boundary between local school districts, and students are not routinely transported across the Norman Wood Bridge to attend school. While accommodation for regular school transportation is not expected to be necessary, potential impacts to after-school activities and special events would be considered as part of future traffic management analysis and planning.

During the study phase, the project team worked with local businesses to better understand their transportation needs and reliance on the bridge. Potential impacts to business access are an important consideration in the evaluation of alternatives, and efforts will continue throughout project development to minimize disruptions and be refined after the study is accepted and approved.  

During the study phase, the project team worked with local businesses to better understand their transportation needs and reliance on the bridge. Potential impacts to business access are an important consideration in the evaluation of alternatives, and efforts will continue throughout project development to minimize disruptions and be refined after the study is accepted and approved.  

The project team has engaged with Old Order communities to better understand the use of the bridge by horse-drawn carriages, and those needs will continue to be an important factor in the design of the selected alternative.  Potential accommodations evaluated as part of the study include adjustments to temporary traffic control operations, such as longer signal clearance intervals to better accommodate horse-drawn carriages. Further coordination with the Old Order communities to determine how horse-drawn carriage traffic impacts can be minimized will occur and be refined after the study is accepted and approved.  

The existing bridge was not designed to safely accommodate pedestrian or bicycle traffic, and its narrow shoulders limit opportunities for these modes of travel.  As a result, accommodation for recreational trail users, bicyclists, and pedestrians has not been incorporated into the alternatives currently under consideration. The project team will continue to coordinate with stakeholders, including the Lancaster Hiking Club, and be refined after the study is accepted and approved.  

No. Dedicated lanes for horse-drawn carriages, buggies, pedestrians or bicyclists have not been incorporated into the alternatives being evaluated. However, wider shoulders are being considered to improve operational flexibility and to accommodate maintenance and emergency needs.

No. An overlook for pedestrians is not currently included in the alternatives being evaluated.    

The existing bridge does not include any highway lighting and lighting needs were not evaluated as part of this planning study. Once a preferred alternative is selected, additional analysis will be completed to determine the need for lighting.

Contact Information

Pharon Bertsch
Senior Project Manger
717-705-6209
pbertsch@pa.gov

Mike Crochunis
Media Contact
717-418-5017
mcrochunis@pa.gov

Fritzi Schreffler
Media Contact
717-787-4335
fschreffle@pa.gov

Accessibility

The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.

Title VI

Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.