Project Status
Step 2 of 4
Design
Next Step: Construction
Public Outreach
Virtual Plans Display
The virtual plans display will be available online from November 23, 2026 through December 23, 2026.
Public Comment Period
The public comment period, where the community is encouraged to respond with questions and concerns will be from November 23, 2026 through December 23, 2026.
Project Overview
County: Lancaster
Municipality: Colerain Township
State Route: Route 2015-012
Local Name: Pumping Station Road
Project Type: Bridge Replacement
MPMS Number: 91395
Proposed Construction Start: May 2028
Proposed Construction End: October 2028
Last Updated: November 2026
The project includes the full replacement of the existing bridge and approach roadway pavement work of the Route 2015 Section 012 (Pumping Station Road) bridge over Bowery Run in Colerain Township, Lancaster County. The purpose of this project is to provide a continued safe and efficient crossing on Route 2015 over Bowery Run.
Within the project area, Route 2015 is a two-lane roadway located in a predominately wooded setting on rolling terrain and is classified as a Rural Minor Collector. No wetlands and two water courses were delineated within the study area. No bicycle or pedestrian facilities exist within the project limits. The roadway within the project limits has a posted speed limit of 35 miles per hour and an average daily traffic volume of 410 vehicles per day.
The existing structure was built in 1941. The width of existing bridge is 29 feet.
The project includes full replacement of the existing bridge. The existing rolled steel multi-beam bridge will be replaced with a prestressed concrete Spread Box Beam bridge that is supported on new abutments. The foundation type is to be determined. The bridge conveys a horizontally curved roadway, but the deck has a non-curved alignment. The roadway will be reconstructed at full depth over approximately 40 feet of the south approach and 63 feet of the north approach. The proposed bridge provides a nearly 31 percent larger hydraulic opening than the existing bridge and the roadway profile matches existing conditions with minor adjustments.
Route 2015 will be detoured during construction.
The project is currently in design, and construction is expected to occur during the 2028 construction season.
The purpose of the plans display is to introduce the project and solicit public input, questions, or concerns regarding the project.
Additional Project Information
Environmental
The project is in a predominately wooded setting on rolling terrain. The land use features in the vicinity of the study area include wooded lots and hillsides, Bowery Run, West Branch Octoraro Creek, driveways and Route 2015-012. No wetlands and two water courses were delineated within the study area. No bicycle or pedestrian facilities exist within the project limits.
A PNDI search indicated the possible presence of endangered bats. A Bat Survey was conducted and concluded that bats are not using the existing bridge as a roosting habitat.
A phase 1 bog turtle habitat assessment was conducted and concluded that there were no wetlands present, and the waterways are not considered potential travel corridors for the species.
A Historic Resource Survey was conducted for J.M. Ecklin House and the building was deemed to be not eligible for the National Register.
Utilities
A utility meeting was conducted on February 11, 2026. A conflict was identified with a pole located in the near right quadrant. The pole is owned by Frontier and occupied by PPL. The pole will most likely be relocated to the north of its present location.
PA American Water owns an abandoned 24-inch cast iron pipe in the area. The pipe was drained approximately 10 years ago.
Right-of-way
Permanent and temporary right-of-way acquisitions are anticipated to allow the construction of the project.
Maintenance and Protection of Traffic
Route 2015 will be closed within the project limits for the duration of construction. A proposed 6.55-mile detour including PA 472, PA 372 and Route 2015 will be utilized.
Schedule and Cost
Overall construction is anticipated to last approximately 4 to 6 months during the spring and summer of 2028 at an estimated cost of $1,861,000
Contact Information
John Schulze
Project Manager
717-540-6040
c-jschulze@pa.gov.
Mike Crochunis
Media Contact
717-418-5017
mcrochunis@pa.gov
Natalie Scott
Media Contact
717-418-5018
natascott@pa.gov
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.