Project Status
Step 2 of 4
Design
Next Step: Construction
Project Overview
County: Susquehanna
Municipality: Plains Township
State Route: 2036
Project Type: Bridge Replacement
MPMS Number: 9643
Proposed Construction Start: Fall 2027
Proposed Construction End: Fall 2028
Last Updated: December 17, 2025
The project consists of replacing the existing 78” pipe carrying Rock Creek in Gibson Township with a two-lane, precast reinforced concrete box culvert along with a retaining wall. The project also includes minor approach roadway work, including driveway and intersection grading and guide rail updates. The proposed typical roadway section on Route 2036 will consist of two 9’ lanes and 2’ shoulders in each direction.
Construction work is anticipated to take place in Fall 2027
Additional Project Information
Detour Routes
Traffic will be detoured throughout construction by utilizing a signed detour. The 5-mile detour will utilize Route 2046 (Fiddle Lake Road) and Route 2077 (Ridge Road).
Contact Information
Donald Rau
Project Manger
570-963-4050
drau@pa.gov
Jessica Ruddy
PennDOT Press Officer
570-963-4044
jeruddy@pa.gov
Past Public Outreach
Public Meeting
Public Plans Display was held:
Date: Monday, January 6, 2025
Time: 7:00 PM
Location: Gibson Township Municipal Building
11452 State Route 92
South Gibson, PA 18842
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.