Project Status
Step 2 of 4
Design
Next Step: Construction
Public Outreach
Virtual Plans Display
The virtual plans display will be available online from June 12, 2026 through June 26, 2026.
Public Comment Period
The public comment period, where the community is encouraged to respond with questions and concerns will be from June 12, 2026 through June 26, 2026.
Project Overview
County: Lancaster County
Municipality: East Lampeter Township
State Route: Route 340-BRC
Local Name: Old Philadelphia Pike
Project Type: Bridge Maintenance
MPMS Number: 119211
Proposed Construction Start: Spring 2027
Proposed Construction End: Fall 2027
Last Updated: May 2026
The Pennsylvania Department of Transportation (PennDOT) invites the public to an online plan display regarding the Route 340 (Old Philadelphia Pike) bridge maintenance project.
The project is located over Mill Creek in East Lampeter Township, Lancaster County, approximately 7 miles east of Lancaster.
The purpose of the project is to perform bridge maintenance activities to extend the service life of the structure and continue to provide a safe crossing for the traveling public.
The project maintenance activities include, but are not limited to: zone repainting, vegetation removal to facilitate repainting, flushing and extending scuppers, and resealing bridge asphalt joint.
To successfully perform the maintenance activities, short- and long-term traffic control is expected. There will be no reduction in number of lanes.
The project is currently in design and construction is anticipated to take place during the 2027 construction season.
Additional Project Information
Environmental
The project is located approximately seven miles east of Lancaster in a mixed rural and suburban setting with the adjacent land use commercial, agricultural, and residential. No wetlands were located near the existing bridge location. Coordination for the Indiana bat will be included as part of the project. No identified historic resources, public parks, state forests, or state gamelands are anticipated to be impacted by the project. There is no documented hazardous, residual, or municipal waste near the immediate project area.
Utilities
There are several overhead utilities located on the north side of the bridge. These include PPL power lines and Comcast communication lines. No impacts are expected to these utilities. UGI has an underground gas line and East Lampeter Township has a sanitary sewer line on the south side of the bridge. No impacts are expected to these utilities.
Right-of-Way
All maintenance activities will be completed within existing right-of-way.
Maintenance and Protection of Traffic
To successfully perform the maintenance activities, short and long-term traffic control is expected. There will be no reduction in number of lanes.
Schedule and Cost
Construction is anticipated to be during the 2027 construction season at an estimated cost of $200,000.
Contact Information
Brandy Rotz
Consultant Project Manager
717-775-3277
c-brotz@pa.gov
Mike Crochunis
Media Contact
717-418-5017
mcrochunis@pa.gov
Fritzi Schreffler
Media Contact
717-418-5016
fschreffle@pa.gov
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.