Project Status
Step 2 of 4
Design
Next Step: Construction
Public Outreach
Virtual Plans Display
The virtual plans display will be available online from June 18, 2026 through July 2, 2026.
Public Comment Period
The public comment period, where the community is encouraged to respond with questions and concerns will be from June 18, 2026 through July 2, 2026.
Project Overview
County: Fayette
Municipality: North & South Union Township
State Route: 119. 1022, 1051, 1069, 2031
Local Name: Bethelboro Road, Connellsville Road, Rolling Hills Estate Road, Bute Road, Main Street, and Dixon Road
Project Type: Preservation
MPMS Number: 122364
Proposed Construction Start: Fall 2026
Proposed Construction End: Fall 2027
Last Updated: 06/18/2026
This project is for the bridge preservation of six structures in Fayette County. Work will consist of an epoxy overlay of the existing concrete deck, expansion dam repair/replacement for three structures and concrete repairs to all substructures at the following sites:
Contact Information
Michael Temoshenka
Project Manager
724-439-7432
mtemoshenk@pa.gov
Melissa Maczko
Media Inquiries
724-415-3748
mmaczko@pa.gov
Andrew Stacy
General Inquiries
724-415-3710
anstacy@pa.gov
Traffic will be maintained during construction with minor shoulder closures on Route 1063 for approximately four weeks and temporary lane closures on Route 119 in approximately four hour intervals. The existing expansion joints seals will be fully replaced on Route 119. Concrete repairs to Piers at all locations and minor shoulder closures on Route 1063 will be required to repair the Piers.
Traffic will be maintained during construction with minor shoulder closures on Route 2027 for approximately four weeks and temporary lane closures on Route 119 in approximately four hour intervals. The existing expansion joints seals will be fully replaced on Route 119. Concrete repairs to Piers at all locations and minor shoulder closures on Route 2027 will be required to repair the Piers.
Traffic will be maintained during construction with minor shoulder closures on Route 119 for approximately four weeks. Concrete repairs to Piers at all locations and minor shoulder closures on Route 119 will be required to repair the Piers.
Traffic will be maintained during construction with minor shoulder closures on Route 119 for approximately four weeks. Concrete repairs to Piers at all locations and minor shoulder closures on Route 119 will be required to repair the Piers.
Traffic will be maintained during Construction with minor shoulder closures on Route 119 for approximately four weeks. Concrete repairs to Piers at all locations and minor shoulder closures on Route 119 will be required to repair the Piers.
Traffic will be maintained during construction with minor shoulder closures on Route 119 for approximately four weeks. Concrete repairs to Piers at all locations and minor shoulder closures on Route 119 will be required to repair the Piers. Minor lane closures will be maintained on Dixon Boulevard to place an epoxy overlay on the deck and replace the seals. Closures will be for eight hours and flaggers will be posted during the placements.
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.