District 8 Projects - Lancaster County

Spruce Grove Road (Route 2007) over Octoraro Lake Bridge Superstructure Replacement

Project Status

Step 2 of 4

Design

Next Step:  Construction

Public Outreach

Virtual Plans Display

​The virtual plans display will be available online from November 23, 2026 through December 23, 2026. 

Public Comment Period

The public comment period, where the community is encouraged to respond with questions and concerns will be from November 23, 2026 through December 23, 2026. 

Project Overview

County: Lancaster
Municipality: Colerain and Little Britain Township
State Route: Route 2007-015
Local Name: Spruce Grove Road
Project Type: Bridge Superstructure Replacement
MPMS Number: 101044
Proposed Construction Start:  May 2028
Proposed Construction End:  October 2028
Last Updated: November 2026

The project includes the replacement of the existing bridge superstructure and approach roadway pavement work of the Route 2007 Section 015 (Spruce Grove Road) bridge over Octoraro Lake in Colerain and Little Britain Townships, Lancaster County. The purpose of this project is to provide a continued safe and efficient crossing on Route 2007 over Octoraro Lake.

Within the project area, Route 2007 is a two-lane roadway (one-lane bridge) located in a predominately wooded setting on rolling terrain and is classified as a Rural Major Collector. The land use features in the vicinity of the study area include wooded lots, Octoraro Lake, Blue Gill Road, and Route 2007-015. No wetlands and one watercourse were delineated within the study area. The roadway within project limits has a posted speed limit of 45 miles per hour and an average daily traffic volume of 542 vehicles per day.

The existing structure was built in 1950. The width of existing bridge is 19 feet.

The existing structure is a three-span continuous steel I-beam bridge. The project will replace the existing steel beams and a concrete deck with new steel beams and a new concrete deck. The existing steel railings will be replaced with new concrete barriers. The roadway will be reconstructed at full depth over approximately 27 feet at the near approach and 25 feet at the far approach. The horizontal and vertical geometry will closely match the existing geometry.

Route 2007 will be detoured during construction.

The project is currently in design, and construction is expected to occur during the 2028 construction season.

The purpose of the plans display is to introduce the project and solicit public input, questions, or concerns regarding the project.

Additional Project Information

Environmental

The project is in a predominately wooded setting on rolling terrain and is classified as a Rural Major Collector. The land use/land cover features in the vicinity of the study area include wooded lots, West Branch Octoraro Creek/Lake, Blue Gill Road, and Route 2007-015. No wetlands and one watercourse were delineated within the study area. No bicycle or pedestrian facilities exist within the project limits.

A PNDI search indicated the possible presence of endangered bats. A Bat Survey was conducted and concluded that bats are not using the existing bridge as a roosting habitat.

A phase 1 bog turtle habitat assessment was conducted and concluded that there is one wetland present and the waterway is not considered a potential travel corridor for the species.

Utilities

A utility meeting was conducted on February 11, 2026. The only utility identified was an overhead line on the south side of the roadway. The line is owned by Frontier and carries low-voltage copper and fiber optic lines. The lines will be protected in place.

Right-of-way

Permanent and temporary right-of-way acquisitions are anticipated to allow the construction of the project.

Maintenance and Protection of Traffic

Route 2007 will be closed within the project limits for the duration of construction. A proposed 5.6-mile detour including Ashville Road, Route 3001 (Forge Road), Route 3008 (Street Road), and PA Route 472 (Lancaster Pike/Kirkwood Pike) will be utilized.

Schedule and Cost

Overall construction is anticipated to last approximately 4 to 6 months during the spring and summer of 2028 at an estimated cost of $1,902,000.00.

Contact Information

John Schulze
Project Manager
717-540-6040
c-jschulze@pa.gov.

Mike Crochunis
Media Contact
717-418-5017
mcrochunis@pa.gov

Natalie Scott
Media Contact
717-418-5018
natascott@pa.gov

Accessibility

The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.

Title VI

Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.