PROJECT UPDATE
October 14, 2026
Route 3104 (Mt. Airy Drive) Bridge Project over U.S. 219 in Richland Township, Cambria County, nearing October 31 Completion Target
The Pennsylvania Department of Transportation (PennDOT) is informing drivers that the closure and detour Route 3104 (Mt. Airy Drive) for a bridge rehabilitation project in Richland Township, Cambria County, is tentatively scheduled to end Saturday, October 31, 2026.
Mt. Airy Drive remains closed with traffic using a 2.9-mile detour on Route 3033 (Solomon Run Road), Route 3031 (Galleria Drive) and Oakridge Drive, and traffic on U.S. 219 beneath the bridge remains under single-lane restriction both northbound and southbound.
Over the next two weeks, contractors will be pouring concrete for the bridge and applying a protective coating to concrete surfaces, with paving scheduled for Monday, October 26, and Tuesday, October 27, weather permitting.
Anticipated Completion Date: Saturday, October 31, 2025
Project Overview
County: Cambria County
Municipality: Richland Township
State Route: Route 3104 and U.S. 219
Local Name: Mt Airy Drive
Project Type: Bridge Rehabilitation
MPMS Number: 114043
Proposed Construction Start: March 2026
Proposed Construction End: October 2026
Last Updated: March 2026
The Pennsylvania Department of Transportation (PennDOT) is beginning construction on the Route 3104 (Mt. Airy Drive) Section 02B over U.S. 219 Bridge Rehabilitation Project in Richland Township, Cambria County.
The project will involve the complete replacement of the bridge superstructure (the deck, girders, and beams above the substructure) and repairs to the substructure (the columns, abutments and/or foundation that carries the bridge load). Minor approach roadway paving to tie into the structure along with guide rail updates will be included.
Mt. Airy Drive traffic will use a detour for the duration of construction to allow the contractor full access to the bridge. Short-term overnight detours of U.S. 219 will be utilized for work activities related to bridge demolition and beam erection.
Contact Information
James F. Bittner Jr.
Project Manager
814-696-7184
Jay Knarr
Media Contact
814-696-7101
jaknarr@pa.gov
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.