Hays Grove Road over Yellow Breeches Creek Bridge Replacement

Project Status

Step 2 of 4

Design

Next Step:  Construction

Public Outreach

Virtual Plans Display

​The virtual plans display will be available online from August 4, 2025 through September 4, 2025

Public Comment Period

The public comment period, where the community is encouraged to respond with questions and concerns will be from August 4, 2025 through September 4, 2025

Project Overview

County: Cumberland
Municipality: Penn Township
State Route: 3011-010
Local Name: Hays Grove Road over Yellow Breeches Creek
Project Type: Bridge Replacement
MPMS#: 90749
Proposed Construction Start: Spring 228
Proposed Construction End: Fall 2028
Last Updated: August 2025

This project involves the replacement of the structure carrying Hays Grove Road (Route 3011) over Yellow Breeches Creek in Penn Township, Cumberland County. The purpose of this project is to maintain a safe crossing on Route3011 over Yellow Breeches Creek.

The existing structure was built in 1914 and is a single-span reinforced concrete slab bridge supported on concrete abutments at a 75-degree skew. The existing structure features a 12-foot normal clear span with a 15-foot, 6-inch curb-to-curb width.

The proposed replacement structure will be a 15-foot by 4-foot precast concrete box culvert with precast end sections and Steel Rail bridge barrier (Pennsylvania 3-Rail). Additional work includes placing rock scour protection at the outlets, reconstructing the pavement along the roadway tie-ins, and installing Manual for Assessing Safety Hardware (MASH)-compliant guide rail. The pavement beyond the full-depth reconstruction limits will be milled and overlaid. The proposed bridge width will match the existing approach roadway widths, which features two (2) 10-foot lanes and 2-foot shoulders.

This section of Hays Grove Road has an estimated average daily traffic volume of 148 vehicles per day (vpd).

The potential 6.2-mile detour will utilize Pine Road (Route 3006), Centerville Road (Route 233), and Walnut Bottom Road (Route 174). Please refer to the project’s Detour Plan graphic. Access to all driveways within the project limits will be maintained during construction. Overhead utilities are present at the site and utility impacts are anticipated to accommodate culvert construction. Utility coordination is ongoing.

The project is currently in design, and construction is anticipated to begin in Spring 2028 and last until the Fall of 2028.

The purpose of the plans display is to introduce the project and solicit public input, questions, or concerns regarding the project.

Contact Information

Justin Gochenaur
Project Manager
717-221-2010
c-jgochena@pa.gov

David M. Thompson
Media Contact
(717) 787-1446
dmthompson@pa.gov

Accessibility

The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.

Title VI

Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.