A public meeting featuring a public plans display and project presentation will take place:
Date: September 23, 2026
Time: 6:00 PM
Location: Chamber of Commerce Building, 32 Commercial Street, Honesdale, PA 18431
Virtual Plans Display
The virtual plans display will be available online from September 14, 2026 through October 14, 2026.
The purpose of the plans display is to introduce the project, display and describe the planned detour, and receive public input regarding questions or concerns with the project. The public is encouraged to respond to the public questionnaire and provide comments by clicking on the Submit A Comment link below.
Public Comment Period
The public comment period, where the community is encouraged to respond with questions and concerns will be from September 14, 2026 through October 14, 2026.
Project Overview
County: Wayne
Municipality: Honesdale Borough
State Route: 6
Local Name: West Park Street
Project Type: Highway Safety Improvement
MPMS Number: 115572
Proposed Construction Start: Fall 2027
Proposed Construction End: Fall 2028
Last Updated: September 14, 2027
The Route 6 Section IMP project is a proposed intersection improvement project in Honesdale Borough in Wayne County, PA. The purpose of the proposed project is to improve safety at the intersection of West Park Street (Route 6) and Maple Avenue (Route 3032), including access management of driveways near the intersection. The existing intersection is currently a minor road stop-controlled intersection on a severe skew. The project involves realigning the minor approach to be more perpendicular as well as adding an exclusive left-turn lane on West Park Street (Route 6.). The intersection will remain minor road stop control with a more defined separation from an adjacent commercial driveway. Additionally, the project will include the replacement of the guide rail, roadway, and signing and pavement markings that are impacted by construction.
Additional Project Information
A detour for Maple Avenue (Route 3032) will be required during the final long-term stage of reconstruction. Maple Avenue (Route 3032) will be closed between the Wayne Health Services parking lot on the north side of Maple Avenue and the intersection with West Park Street (Route 6). The 0.9 mile detour redirects traffic onto Maple Avenue West Park Street to avoid the closed area. West Park Street (Route 6) will be open to traffic during construction using staged construction methods.
It is anticipated that construction will begin late 2027 and will be complete by fall of 2028. The Maple Avenue (Route 3032 detour will take place during the summer of 2028.
Contact Information
Lou Spaciano, PE
Project Manager
c-lspacian@pa.gov
Jessica Ruddy
Community Relations Coordinator
jeruddy@pa.gov
Past Public Outreach
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.