Route 4007 (Miller Road) over Ackerly Creek Structure Project

Project Status

Step 2 of 4

Design

Next Step:  Construction

Public Outreach

Public Meeting

A public meeting featuring a public plans display and project presentation will take place:

Date: March 10, 2026
Time: 6:00 PM
Location:  Waverly Township Building (8 Lake Henry Dr, Waverly, PA 18471) 

Virtual Plans Display

​The virtual plans display will be available online from February 24, 2026, through March 24, 2026.  

Public Comment Period

The public comment period, where the community is encouraged to respond with questions and concerns will be from February 24, 2026, through March 24, 2026.  

Project Overview

County: Lackawanna
Municipality: Waverly Towsnhip
State Route: 4007
Local Name: Miller Road
Project Type: Structure Replacement
MPMS Number: 8383
Proposed Construction Start: Spring 2028
Proposed Construction End: Fall 2028
Last Updated: February 17, 2026

The Pennsylvania Department of Transportation (PennDOT) invites the public to a joint, in-person and virtual plans display regarding the Route 4007 (Miller Road), Section 270 Structure Replacement Project over Ackerly Creek. The joint, in-person public meeting will take place on Tuesday March 10, 2026, at the Waverly Township Building (8 Lake Henry Dr, Waverly, PA 18471) at 6:00 PM during the Township’s regularly scheduled monthly Township Supervisors’ Meeting.

The purpose of this project is to address the deficiencies of the existing structure and provide continued safe and efficient crossing of Ackerly Creek.

The Route 4007-270 project consists of replacing the existing stone masonry closed spandrel arch culvert with a precast concrete box culvert. The reconstructed Route 4007 roadway (Miller Rd) and structure will consist of two 11’-0” travel lanes with 3’-0” shoulders.

Additional work includes, but is not limited to: approach roadway reconstruction, guide rail upgrades, drainage improvements, grading, signing, and pavement markings. One utility line relocation is also anticipated as part of the project.

Traffic will be maintained through a detour during construction. The proposed 2.0-mile detour will utilize all state routes.

The project is currently in the preliminary design phase. It is anticipated that construction will begin in the spring of 2028 and will be completed by the fall of 2028.

Additional Project Information

Route 4007 detour directions:

The roadway at the bridge site will be closed to all traffic and detoured during construction. The detour is expected to be in place for approximately three months.

Beginning south of the project, the vehicle detour will follow Route 407 North (Abington Road) until reaching Route 632 East (Carbondale Road). Travelers will turn right onto PA-632 East (Carbondale Road) and then continue until connecting back onto Route 4007 (Miller Road) for a total detour length of approximately 2 miles.

Contact Information

Thomas Capitano
Project Manager
570- 614-295
tcapitano@pa.gov

Jessica Ruddy
Community Relations Coordinator
570-963-4044
jeruddy@pa.gov

Press Release Archive

Related Projects

Accessibility

The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.

Title VI

Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.