Project Overview
County: Allegheny
Municipality: City of Pittsburgh
State Route: I-376
Local Name: Commercial Street Bridge
Project Type: Bridge Replacement
Construction Start: 2024
Construction End: Summer 2027
Last Updated: 07/10/2026
The Commercial Street Bridge Replacement Project will utilize Accelerated Bridge Construction Techniques to laterally slide the new bridge onto the existing alignment of I-376 (Parkway East), which would be one of the largest lateral slide projects performed in Pennsylvania. The $95 million project located between the Edgewood/Swissvale (Exit 77) interchange and Squirrel Hill Tunnel in Edgewood and Swissvale boroughs, and the City of Pittsburgh began in June of 2024 with the reconstruction of the westbound I-376 off-ramp to Forest Hills/Wilkinsburg (Exit 78B). Tentatively, from July 10 through August 3, 2026, drivers can expect a 25-day full closure and detour of I-376. The overall project is anticipated to conclude in the summer of 2027.
Attention Travelers: I-376 Closure Begins July 10 at 9:00 p.m.
A 25-day closure on I-376 Parkway East in Edgewood Borough and the City of Pittsburgh, Allegheny County, will occur July 10 - August 3.
A full closure of I-376 in each direction between the Squirrel Hill Tunnel and the Edgewood/Swissvale (Exit 77) interchange will occur around-the-clock from 9:00 p.m. Friday, July 10 through 5:00 a.m. Monday, August 3 as crews demolish and replace the I-376 Commercial Street Bridge. Traffic will be detoured.
Contact Information
General Questions or Inquiries:
CommStBridgeProject@pa.gov
Media Inquiries:
Yasmeen Manyisha
Press Officer
ymanyisha@pa.gov
Project Status
Step 3 of 4
Construction
Next Step: Completed
Artist Renderings of Project
How will the 11,000-ton bridge be slid into place?
Check out the animation below or view on our YouTube channel.
-
I-376 Bathtub Floodwall Reconstruction Project
-
I-376 Parkway East Bridge over Four Mile Run Feasibility Study
-
I-376 Parkway East – Churchill to Monroeville
-
I-376 Parkway East – Commercial Street Bridge Replacement
-
I-376 Parkway East – Edgewood to Churchill Betterment Project
-
I-376 Parkway East – Squirrel Hill Interchange Improvement Project
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.