Montoursville, PA – Motorists are advised that a two-year highway improvement project continues on Interstate 180 in the City of Williamsport, Loyalsock Township, Fairfield Township, and Montoursville Borough, Lycoming County.
The week of Sunday, August 31, 2025
Interstate-180
- (New) Guide rail replacement will begin at various locations along Interstate 180 in both directions between the Basin Street Interchange (Exit 26) in the City of Williamsport and the Montoursville / Warrensville Road Interchange (Exit 22 / Route 2022) in the Borough of Montoursville.
- (New) On Saturday, September 6 and Sunday, September 7, bridge preservation work will be performed the bridges carrying Interstate 180 over the Loyalsock Creek and the bridge carrying Northway Road (Route 2029) over Millers Run in Loyalsock Township.
- Motorists can expect alternating lane restrictions between the hours of 7:00 PM and 6:00 AM, where work is being performed.
Montoursville/Warrensville Road Interchange
- Highway lighting work continues at the Montoursville/Warrensville Road eastbound Interchange (Exit 22) in the Borough of Montoursville.
- No impacts to traffic are expects, work will be performed outside the shoulder area between the hours of 6:00 AM and 3:00 PM.
Faxon Road Interchange
- (New) Highway lighting work will be performed at the Faxon Interchange (Exit 25 / Northway Road) in Loyalsock Township.
- No impacts to traffic are expects, work will be performed outside the shoulder area between the hours of 6:00 AM and 3:00 PM.
Motorists should be alert, slow down, and drive with caution through the work zone.
Glenn O. Hawbaker is the prime contractor for this two-year, $14 million, highway improvement project on Interstate 180 between Brushy Ridge Road (Route 2026) in Fairfield Township and the Route 15 interchange in the City of Williamsport. Work on the project includes the mill and resurface of 11 miles of I-180 between Basin Street (Route 2062) and Warrensville Road (Route 2022), this work includes the Faxon (Exit 25) and Route 15 (Exit 29) interchanges, base repairs, high friction surface treatment, tree removal, drainage upgrades, guide rail and signal upgrades. Additional work includes updated highway lighting, bridge preservation work, and pavement markings. Work on the project is anticipated to be completed in the fall 2026 and includes a winter shutdown.
Motorists can check conditions on major roadways by visiting www.511PA.com.
511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional X alerts.
Subscribe to PennDOT news and traffic alerts in Tioga, Bradford, Lycoming, Sullivan, Union, Snyder, Northumberland, Montour, and Columbia counties at www.penndot.pa.gov/District3.
Information about infrastructure in District 3 including completed work and significant projects, is available at www.penndot.pa.gov/D3Results. Find PennDOT’s planned and active construction projects at www.projects.penndot.pa.gov.
Follow PennDOT news on X, Facebook and Instagram.
MEDIA CONTACTS: Maggie Baker and Kim Smith at ra-pdd03crc@pa.gov
# # #