Project Overview
County: Carbon and Luzerne
State Route: SR 0080-08B (Interstate 80)
Local Name: I-80 Over Lehigh River Bridge Project
Project Type: Bridge Replacement
Design and Construction Cost: $148.9 million
Start of Construction: June 2024
Anticipated Bridge Completion: Summer 2028
Designer: Michael Baker International
Last Updated: June 2025
The I-80 bridges over the Lehigh River are eastbound/westbound structures built in 1965 and approaching the end of their serviceable lifespans. These bridges cross over the Lehigh River, Lehigh Gorge State Park, Reading Blue Mountain and Northern Railroad and SR 1005 (River Road) in Carbon and Luzerne Counties. Combined, the bridges carry an average of 27,400 vehicles per day, about 44 percent of which is truck traffic.
The purpose of the I-80 Over Lehigh River Bridges project is to address the deterioration of the aging bridge structures and provide safe and reliable bridges that will provide connectivity for interstate travelers, commuters, commercial users, emergency services, tourists, and local residents. The project will replace the aging bridges with wider structures; increase the length of the eastbound on-ramp auxiliary lane, the height of the bridges' barriers, and the width of the shoulders to meet current interstate design standards; and improve safety in the corridor.
Spring 2025 Updates
PA 940 On-Ramp Closure Supports Critical I-80 Bridge Improvements
As part of the ongoing I-80 Over Lehigh River Bridge Replacement Project, the closure of the PA 940 on-ramp to Interstate 80 East (Exit 273), which began in April, remains in effect. This temporary closure is a key component of the project’s current construction phase and plays a vital role in supporting safe and efficient progress on the overall bridge and roadway improvements.
Construction Progress – Piers 1–3, I-80 over Lehigh River
Ongoing construction of Piers 1, 2, and 3 for the new I-80 bridge over the Lehigh River. Pier 1 is in the early stages with formwork and rebar placement, Pier 2 shows progressed column work, and Pier 3 foundation activity is underway.
Rebar Cage Lift and Placement – Pier 1, I-80 Lehigh River Project
Crews have successfully lifted and placed a rebar cage at Pier 1 as part of the I-80 Over Lehigh River Bridge Replacement Project. This key step strengthens the pier’s foundation and prepares it for upcoming concrete work.
-
Project Area Map (PDF)
-
What is the National Environmental Policy Act?
-
What is a Categorical Exclusion (CE)?
-
Approved Categorical Exclusion - October 2022
-
I-80 Over Lehigh River Bridge Categorical Exclusion Information - Fall 2022
-
March 7, 2024 I-80 Over Lehigh River Bridge Pre-Construction Public Meeting Presentation