2025 Detours
Blair County
- Scope: Structure replacement
- Traffic Control: Detour (2.2 miles)
- Construction Timeframe: April – December 2025
- Detour Implementation Date: June 24, 2025
- Anticipated Date Detour to be Lifted: October 2025
- Contractor: Cottle’s Asphalt Maintenance, Inc.
- Current Contract: $7,434,773 (Bid with PA 36 Frankstown Road to Mill Run Road)
View Route 36 Mill Run Bridge Map (PDF).
- Scope: Structure replacement
- Traffic Control: Detour (8.1 miles)
- Construction Timeframe: June – July 2026
- Detour Implementation Date: June 2, 2026
- Anticipated Date Detour to be Lifted: July 7, 2026
- Contractor: Glenn O. Hawbaker, Inc.
- Current Contract: $5,136,136 (Bid with Route 3013 Blair Gap Run Bridge)
View Route 3013 Dry Run Bridge Map (PDF).
Bedford County
- Scope: Structure Replacement
- Traffic Control: Detour – 13.5 miles – Anticipated less than 40 days during school recess
- Construction Timeframe: May – August 2025
- Detour Implementation Date: July 21, 2025
- Anticipated Date Detour to be Lifted: August 18, 2025
- Contractor: Wen-Brooke Contracting Inc.
- Current Contract: $1,005,163
View the Route 26 over Ravers Run Map (PDF).
- Scope: Structure Replacement and Traffic Signal Upgrade
- Traffic Control: Detour – 13.0 miles – Anticipated 112 days
- Construction Timeframe: May – October 2025
- Detour Implementation Date: June 2025 (after end 2024-25 school term)
- Anticipated Date Detour to be Lifted: September 22, 2025
- Contractor: Wen-Brooke Contracting Inc.
- Current Contract: $1,618,291
View the Manns Choice Buffalo Run Map (PDF).
Cambria County
- Scope: Bridge rehab - Design/Build
- Detour Length: East and Westboud Lanes, 6.3 miles
- Construction Timeframe: As early as Spring 2024 - August 2025
- Anticipated Detour Implementation Date: April 7, 2025
- Anticipated Date Detour to be Lifted: May 9, 2025
- Contractor: Charles J. Merlo, Inc.
- Current Contract: $3,994,000
View the Route 2019 (Level Road) over U.S. 22 Bridge D/B Project Map (PDF).
- Scope: Bridge Rehabilitation
- Traffic Control: Detour Route 2101 (5.6 miles) and U.S. 22 nighttime closures
- Construction Timeframe: April – October 2025
- Detour Implementation Date: April 2025
- Anticipated Date Detour to be Lifted: October 2025
- Contractor: Plum Contracting, Inc.
- Current Contract: $ 2,888,700.19
View the Route 2101 Cooney Road Bridge Map (PDF).
View the U.S. 22 Overnight Detour Maps for Cooney Road Bridge (PDF).
- Scope: Resurfacing (5.9 miles)
- Traffic Control: Short-term flagging, local street detour (0.3 miles), and pedestrian detour
- Construction Timeframe: April - November 2025
- Anticipated Detour Implementation Date: April 2025
- Anticipated Date Detour to be Lifted: September 2025
- Contractor: Quaker Sales Corporation
- Current Contract: $ 5,199,141
View the U.S. 219 Ditter's Curve Map (PDF).
- Scope: Resurfacing, culvert preservation, and slide correction
- Traffic Control: Short-term flagging with detours of Route 3007 (6.43 miles) and Flora Street (0.25 miles)
- Construction Timeframe: April – October 2025
- Anticipated Detour Implementation Date: July 14, 2025
- Anticipated Date Detour to be Lifted: September 21, 2025
- Contractor: HRI, Inc.
- Current Contract: $ 3,016,909
View the Route 3007 T337 to Route 56 and Flora Street Detour Map (PDF).
- Scope: Bridge Rehabilitation
- Traffic Control: Detour (4.1 miles) 42-day duration
- Construction Timeframe: April – October 2025
- Anticipated Detour Implementation: April 2025
- Anticipated Date Detour to be lifted: May 2025
- Contractor: Cottle’s Asphalt Maintenance, Inc.
- Current Contract: $ 788,754.28 (Bid with Jackson St over NS RR and Oak St Over NS RR)
View the T-510 Marra Road Bridge Map (PDF).
- Scope: Bridge Rehabilitation
- Traffic Control: Detour (3.5 miles) 49-day duration
- Construction Timeframe: April – October 2025
- Anticipated Detour Implementation: May 2025
- Anticipated Date Detour to be lifted: July 2025
- Contractor: Cottle’s Asphalt Maintenance, Inc.
- Current Contract: $ 788,754.28 (Bid with Jackson St over NS RR)
View the Oak Street over Norfolk Southern RR Map (PDF).
Fulton County
- Scope: Structure Replacement – Precast RC Box Culvert
- Traffic Control: Detour – 19.4 Miles – 55 days
- Construction Timeframe: April – November 2025
- Detour Implementation Date: August 2025
- Anticipated Date Detour to be Lifted: October 2025
- Contractor: Wen-Brooke Contracting Inc.
- Current Contract: $1,147,534
View the South Big Cove Tannery Road over Esther Run Map (PDF).
Huntingdon County
- Scope: Structure replacement
- Bid with Route 305 – U.S. 22 to Route 4004
- Traffic Control: Detour (Truck, 40 miles; Local, 0.3 miles)
- Construction Timeframe: April – October 2025
- Detour Implementation Date: Early September 2025 (21-day maximum duration)
- Anticipated Date Detour to be Lifted: By September 27, 2025
- Contractor: Cottle’s Asphalt Maintenance, Inc.
- Current Contract: $2,150,790
View the Route 305 Derry Run Bridge Map (PDF).
Somerset County
- Scope: Paving, the renovation of multiple bridge-structures, and drainage, guide rail and signage upgrades along five (5) miles of U.S. 219 in Somerset County.
- Detours: During the Route 4102 (Sechler Road) bridge-structure renovation, a 6.5-mile detour will divert traffic to Route 281 to Route 4026 (Lake Road) to Route 601 (North Center Avenue) to Gilmour Road (T-861). During the Route 4104 (Critchfield Road / T-626) bridge-structure renovation, a 2.4-mile detour will divert traffic to Route 601 (Penn Avenue) to Route 4004 (Bicycle Road) to Morris Road (T-548). During the 9.4-mile Route 8005 ramps interchange a 14-day detour will use Route 601, Route 4055 and Route 281.
- Construction Timeframe: August 2024 - October 2026
- Detour Implementation Dates: April 7, 2025 for appox. 30 days
- Contractor: New Enterprise Stone & Lime Co., Inc.
- Current Contract: $25,000,000.00
View the Sechler Road Bridge Rehab Project Detour Map (PDF).
View the Route 601 Ramp Interchange Detour Map (PDF).
- Scope: Resurfacing, bridge rehabilitations/replacement, drainage and guide rail upgrades (4.7 miles)
- Traffic Control: Long-term lane closure w/ short-term ramp detours and side road detours at bridge locations
- Construction Timeframe: April 2025 – November 2026
- Contractor: New Enterprise Stone & Lime Co., Inc.
- Current Contract: $ 24,600,000
View the Route 8005 Ramp Interchange Map (PDF).
View the Route 8005 Ramp Projects Map (PDF).
View the US 219 to US 30 Bridges Project Map (PDF).
- Scope: Two Bridge Replacements
- Traffic Control: Detour (12 miles)
- Construction Timeframe: May 2025 – September 2025
- Anticipated Detour Implementation Date: June 10, 2025
- Anticipated Date Detour to be Lifted: August 22, 2025
- Contractor: C.H. & D. Enterprises, Inc.
- Current Contract: $ 2,566,257
View the Route 3001 Cucumber Run Bridge Map (PDF).
- Scope: Bridge Replacement
- Traffic Control: Short-Term Flagging & Detour (15.6 miles)
- Construction Timeframe: April 2025 – October 2025
- Anticipated Detour Implementation Date: July 14, 2025
- Anticipated Date Detour to be Lifted: August 14, 2025
- Contractor: JVI Group, Inc.
- Current Contract: $ 1,102,041
View the Route 601 Hollsopple Bridge Map (PDF).
- Scope: Bridge Replacement
- Traffic Control: Detour (14.1 miles), 76-day duration
- Construction Timeframe: June 2025 – October 2025
- Anticipated Detour Implementation Date: June 11, 2025
- Anticipated Date Detour to be Lifted: August 25, 2025
- Contractor: JVI Group, Inc.
- Current Contract: $ 768,827
View the Route 3007 Humbert Road over Smith Run Bridge Map (PDF).
- Scope: Bridge Replacement
- Traffic Control: Detour (17.2 miles) 17-day duration
- Construction Timeframe: May - September 2025
- Anticipated Detour Implementation Date: June 10, 2025
- Anticipated Date Detour to be Lifted: August 22, 2025
- Contractor: Cottle’s Asphalt Maintenance, Inc.
- Current Contract: $ 851,400
View the Route 4001 Bakersville Edie Road over Moore Run Bridge Map (PDF).
- Scope: Bridge Replacement
- Traffic Control: Detour (0.8 Miles), Ped. Detour (0.4 Miles) 150-day duration
- Construction Timeframe: June – October 2025
- Contractor: A. Merante Contracting Inc.
- Current Contract: $1,218,000
View the Route 7422 24th Street over Seese Run Bridge Map (PDF).
2024 Detours
Cambria County
- Scope: Bridge rehab - Design/Build
- Detour Length: East and Westboud Lanes 6.3 miles
- Construction Timeframe: As early as Spring 2024 - August 2025
- Anticipated Detour Implementation Date: TBD
- Anticipated Date Detour to be Lifted: TBD
- Contractor: Charles J. Merlo, Inc.
- Current Contract: $3,994,000
View the Route 2019 (Level Road) over U.S. 22 Bridge D/B Project Map (PDF).
Somerset County
- Scope: Three Bridge Replacements, One Culvert Replacement
- Detour Length: 12 miles
- Construction Timeframe: April 2024 - September 2025
- Anticipated Detour Implementation Dates: June 11, 2024 & June 10, 2025
- Anticipated Dates Detours to be Lifted: August 23, 2024 & Auust 22, 2025
- Contractor: C.H. & D. Enterprises, Inc.
- Current Contract: $2,566,257
View the Route 3001 Cucumber Run Bridges Project Detour Map (PDF).
- Scope: Resurfacing, Drainage, and Guide Rail Upgrades
- Detour Length: 51 miles
- Construction Timeframe: May 2024 - October 2024
- Anticipated Detour Implementation Dates: TBD - two detours with a 4-day duration and one detour with a 5-day duration
- Anticipated Dates Detours to be Lifted: TBD
- Contractor: New Enterprise Stone and Lime Co.
- Current Contract: $3,349,111
View the PA 31 Barn Swallow Road to Somerset Borough Line Project Detour Map (PDF).