2026 Detours
Blair County

- Scope: Structure replacement
- Traffic Control: Detour (8.1 miles)
- Construction Timeframe: June – July 2026
- Detour Implementation Date: June 2, 2026
- Anticipated Date Detour to be Lifted: July 7, 2026
- Contractor: Glenn O. Hawbaker, Inc.
- Current Contract: $5,136,136 (Bid with Route 3013 Blair Gap Run Bridge)
View Route 3013 Dry Run Bridge Map (PDF).

- Scope: Resurfacing and Slide Stabilization
- Traffic Control: Detour (23.5 miles)
- Construction Timeframe: March 2026 to July 2027
- Detour Implementation Date: March 24, 2026
- Anticipated Date Detour to be Lifted: August 2026
- Contractor: New Enterprise Stone & Lime, New Enterprise, Pa.
- Current Contract: $8,405,252.50
View Route 453 Tyrone Snyder Twp Detour and Project Map (PDF).
Visit the Route 453 Tyrone Snyder Twp Resurfacing and Slide Stabilization Project Page
Cambria County

- Scope: Bridege Rehabilitation
- Traffic Control: Detour (2.9 miles)
- Construction Timeframe: March to October 2026
- Detour Implementation Date: March 30, 2026
- Anticipated Date Detour to be Lifted: October 2026
- Contractor: J.F.Shea Construction, Inc., Mount Pleasant, Pa.
- Current Contract: $2,257,170
View Route 3104 Mt Airy Drive Bridge Rehab Detour Map (PDF).