Atherton Street Update for Start of June

The Pennsylvania Department of Transportation (PennDOT) is providing a start-of-June update for its Atherton Street (Route 3014) project in State College The work zone stretches from Curtin Road to just north of Westerly Parkway. PennDOT anticipates the completion of this three-year project in the fall of 2024. 

Area motorists can expect the following the week of June 5: 

Monday, June 5 through Thursday, June 8, one crew will be installing waterline services and removing old waterline from West Foster Avenue to West Fairmont Avenue.  An alternating traffic pattern will be enforced by roadway flaggers. 

Monday, June 5 through Thursday, June 8, three crews will be working from Clay Lane to Beaver Avenue. Work will include installation of new curb and sidewalk, paving, and installation of conduit and concrete foundations for new highway lighting and traffic signals. This work is within the already closed eastbound lanes and will not further restrict the flow of traffic. 

On Friday, June 9, a new traffic pattern will shift westbound traffic into the two left lanes from Beaver Avenue to Clay Lane. At Clay Lane, traffic will shift back to the two right lanes. Drivers should proceed through this area with caution. During daylight hours, a flagger will be in the roadway to facilitate vehicle movement.

The eastbound closure (both eastbound lanes) on Atherton Street between College Avenue and Beaver Avenue remains in place. This closure is necessary to install new drainage. Eastbound traffic is diverted at College Avenue and uses the Atherton Street downtown detour (North Atherton, West College Avenue, Buckhout Street, Beaver Avenue, South Atherton). This eastbound detour will be in place until early July. One lane of westbound Atherton Street will remain open through the duration of this work. Access to the Graduate Hotel is from the westbound lane. 

Through early July, the left lane of Beaver Avenue remains closed from H Alley to Atherton Street and the left lane of College Avenue remains closed from Burrowes Road to Atherton Street. 

Message boards remain in place alerting motorists to the closures.

A pedestrian detour remains in place. PennDOT reminds pedestrians to use that detour and avoid walking through the construction zone.

Please pay attention to work zone and directional signage to enhance safety and keep traffic moving efficiently. 

Visit the Atherton Street project page at www.penndot.pa.gov/AthertonStreet for mapping of these detours. PennDOT posts regular updates to the project page week-to-week, as work progresses. Detour information is also posted. 

Overall project work will include roadway reconstruction, drainage improvements that include pipes and inlets, water and sewer lines, concrete curbing, sidewalks and detectable warning surfaces, pavement markings, traffic signals and supports, and miscellaneous items.

HRI, Inc. of State College is the contractor on this $30.7 million job. PennDOT reminds drivers all work is weather and schedule dependent. 

PennDOT reminds motorists that traffic may be stopped intermittently for short periods during work activities. Please use caution when traveling through the work zone and do not follow construction equipment into the closed lane. When approaching the work zone, use both lanes to the merge point to minimize traffic back-ups and shorten travel delays. 

Motorists can check conditions on major roadways by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras. 

511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional Twitter alerts accessible on the 511PA website. 

Subscribe to PennDOT news in Cameron, Centre, Clearfield, Clinton, Elk, Juniata, McKean, Mifflin, and Potter counties at www.penndot.gov/District2

Follow PennDOT on Twitter and like the department on Facebook and Instagram.

Contact: Marla Fannin, mfannin@pa.gov or 814.765.0423      

# # #