Project Status
Step 2 of 4
Design
Next Step: Construction
Public Outreach
Public Plans Display
An in-person open house with a public plans display will take place:
Date: Tuesday, June 16, 2026
Time: 5:00 to 8:00 p.m.
Location:
VFW – South Mountain Post 6771
22 West Franklin Street
Dillsburg, PA 17019
Public Comment Period
The public comment period, where the community is encouraged to respond with questions and concerns will be from June 16, 2026, through July 16, 2026.
Project Overview
County: York, Cumberland
Municipality: Carroll Township, Dillsburg Borough, Upper Allen Township
State Route: Route 15
Local Name: Blue & Gray Highway
Project Type: Reconstruction
MPMS Number: 92923
Proposed Construction Start: Fall 2028
Proposed Construction End: Fall 2031
Last Updated: June 2026
PennDOT is currently performing preliminary engineering for the Route 15 Section 044 Reconstruction Project. The project is four miles in length between the Range End Road/Golf Course Road intersection in Carroll Township, York County and continues north through Dillsburg Borough before crossing into Upper Allen Township, Cumberland County and ending north of the Glenn Bowers Memorial Bridge carrying Route 15 over the Yellow Breeches Creek.
The primary proposed improvement includes the full-depth reconstruction of existing Route 15 from the southern project limit north to approximately 600’ south of the Glenn Bowers Memorial Bridge, with the remaining portion of existing roadway being milled and overlaid to the southern end of the bridge. The project also includes bridge preservation improvements of the existing Glenn Bowers Memorial Bridge. Turn lane lengths are being updated to provide adequate storage length, as well as the addition of a third right turn auxiliary lane throughout the majority of the project corridor south of the Ore Bank Road/Spring Lane Road intersection. Additional improvements include updates to existing drainage systems, stormwater facilities, guide rail, upgrade/replacement of existing traffic signals at the four signalized intersections, review of pedestrian accommodations at the four signalized intersections, and reduction of unrestricted access to businesses along the corridor.
Construction activities for the Route 15 (Blue & Gray Highway) Reconstruction project will be staged to minimize disruptions to traffic and maintain access for residents, businesses, and emergency services. Two eleven-foot lanes of Route 15 traffic are anticipated to be maintained in each direction during staged construction except during short-term, off-peak operations. Certain turn movements may possibly need to be detoured at various stages of construction. Business access will be maintained at all times during business hours. Coordination will be ongoing with local municipalities, businesses and emergency responders to ensure continued access and responsiveness throughout all construction phases.
The project is currently in the preliminary engineering phase and physical work is anticipated to take place between the 2028 and 2031 construction seasons, subject to all approvals, environmental clearances, and funding availability.
Contact Information
David Fratangeli
Senior Project Manager
717-705-6176
dfratangel@pa.gov
Fritzi Schreffler
Press Officer
717-787-4335
fschreffle@pa.gov
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.