Montoursville, PA – Motorists are advised that a two-year highway improvement project continues on Interstate 180 in the City of Williamsport, Loyalsock Township, Fairfield Township, and Montoursville Borough, Lycoming County.
Weekend of Friday, September 12, 2025
Interstate-180
- (NEW) Between Friday, September 12 at 7:00 PM and Monday, September 15, at 6:00 AM, the contractor will be applying a sealer on the bridge deck carrying Interstate 80 westbound over the Loyalsock Creek.
- (NEW) Motorists can expect the left (passing) lane to be restricted for the duration of the weekend while the sealer is applied and cures.
- Motorists should be alert, slow down, and drive with caution.
The week of Sunday, September 14, 2025
Montoursville/Warrensville Road Interchange
- Highway lighting work continues at the Montoursville/Warrensville Road eastbound Interchange (Exit 22) in the Borough of Montoursville.
- No impacts to traffic are expects, work will be performed outside the shoulder area between the hours of 6:00 AM and 3:00 PM.
Faxon Road Interchange
- (NEW) On Wednesday, September 17 and Thursday, September 18, the contractor will be placing concrete at the two traffic islands between the Exit 25 (Faxon) exit and entrance ramps and Northway Road. Work will be performed between the hours of 7:00 PM and 6:00 AM.
- Between the hours of Midnight and 5:00 AM, Northway Road will be closed between Shiffler Avenue (Route 2056) and Third Street (Route 2014).
- I-180 westbound traffic will be detoured using Shiffler Avenue and Third Street.
- I-180 eastbound and Commerce Drive traffic will be detoured using Northway Road, Shiffler Avenue, and Third Street.
- Highway lighting work will continue at the Faxon Interchange (Exit 25 / Northway Road) in Loyalsock Township. No impacts to traffic are expected, work will be performed outside the shoulder area between the hours of 6:00 AM and 3:00 PM.
Motorists should be alert, slow down, and drive with caution through the work zone.
Glenn O. Hawbaker is the prime contractor for this two-year, $14 million, highway improvement project on Interstate 180 between Brushy Ridge Road (Route 2026) in Fairfield Township and the Route 15 interchange in the City of Williamsport. Work on the project includes the mill and resurface of 11 miles of I-180 between Basin Street (Route 2062) and Warrensville Road (Route 2022), this work includes the Faxon (Exit 25) and Route 15 (Exit 29) interchanges, base repairs, high friction surface treatment, tree removal, drainage upgrades, guide rail and signal upgrades. Additional work includes updated highway lighting, bridge preservation work, and pavement markings. Work on the project is anticipated to be completed in the fall 2026 and includes a winter shutdown.
Motorists can check conditions on major roadways by visiting www.511PA.com.
511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional X alerts.
Subscribe to PennDOT news and traffic alerts in Tioga, Bradford, Lycoming, Sullivan, Union, Snyder, Northumberland, Montour, and Columbia counties at www.penndot.pa.gov/District3.
Information about infrastructure in District 3 including completed work and significant projects, is available at www.penndot.pa.gov/D3Results. Find PennDOT’s planned and active construction projects at www.projects.penndot.pa.gov.
Follow PennDOT news on X, Facebook and Instagram.
MEDIA CONTACTS: Maggie Baker and Kim Smith at ra-pdd03crc@pa.gov
# # #