Step 3 of 4
Construction
Next Step: Completion
Project Overview
County: Centre County
Municipality: Boggs, Marion, and Spring townships.
State Route: SR 80
Project Type: High Speed Interchange Project
Construction Start: September 2024
Proposed Construction End: September 2030
Last Updated: May 29, 2025
This project will enhance traffic safety by providing a direct connection between Interstates 80 and 99, making it unnecessary to travel along Route 26 (Jacksonville Road) to access them, relieving traffic congestion, and realigning service for local traffic. Overall work includes building the interchange, ten bridges, four retaining walls, five box culverts, seven sign structures, and three changeable message boards. It also includes constructing new and rebuilding existing roadways and ramps, drainage improvements, installing Intelligent Transportation Devices, guide rail and highway lighting, pavement marking, stream improvements, and miscellaneous construction. Work will continue through the next six constructions seasons, ending in September 2030.
Contractor:
Trumbull Corporation of Pittsburgh, PA.
Cost:
$259 million.
Additional Project Information
The high-speed interchange is the next phase of a three-phase project. The first involved the construction of the local access interchange at mile marker 163, which provided direct access between Route 26 and I-80 for local traffic. Construction on that phase occurred over three construction seasons between 2020 and 2022. The contract value was $52 million. That phase benefited from a $35 million federal Infrastructure for Rebuilding American (INFRA) grant.
The other phase will reconstruct and widen Route 26 to maintain and support the State roadway network. It will feature 11-foot travel lanes and 4-foot shoulders. Excavation work for that project started in November. Active construction started on April 1, 2025.
Completing all three phases will support the regional freight economy and improve the reliability of roadway travel throughout the region.
Contact Information
Caleb Meighen
Inspector In Charge
814-389-2134
cameighen@pa.gov
Peter Hall
Assistant Construction Engineer
814-765-0452
pehall@pa.gov
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.