District 5 Projects - Lehigh County

Fish Hatchery Road over Little Lehigh Creek Bridge Replacement Project

Project Status

Step 2 of 4

Design

Next Step:  Construction

Public Outreach

Public Meeting

The public meeting will be held at the regularly scheduled Allentown City Council Meeting on June 18, 2025

Virtual Plans Display

​The virtual plans display will be available online on May 27, 2025

Public Comment Period

The public comment period, where the community is encouraged to respond with questions and concerns will be from May 27, 2025 through  June 27, 2025

Project Overview

County: Lehigh
Municipality: City of Allentown
State Route: 2010
Local Name: Fish Hatchery Road
Project Type: Superstructure Replacement
MPMS Number: 119933
Proposed Construction Start: Summer 2027
Proposed Construction End: Spring 2029

The Pennsylvania Department of Transportation (PennDOT) announces a Plans Display and Project Presentation for the SR 2010, Section 01B Superstructure Replacement project. The proposed project involves the superstructure replacement of the two-lane bridge that carries SR 2010 (Fish Hatchery Road) and a sidewalk over Little Lehigh Creek, in the City of Allentown, Lehigh County.

This project involves the full superstructure replacement of the existing four-span bridge over the Little Lehigh Creek on SR 2010 in the City of Allentown. The existing line and grade will be maintained to the greatest extent possible. The existing structure was originally constructed in 1939 and is not currently posted. The existing bridge has a total length of 172’, a width of 29’-6” with a 5’-0” sidewalk on the downstream side of the structure. The proposed structure will include composite steel I-beams. The proposed structure will have a 170’ total span length, with a width of 33’-1” including a 5’-0” sidewalk on the downstream side that will be protected from vehicular traffic with a concrete barrier. The bridge sidewalk will tie into the adjacent trail network at a more level grade adjacent to the Fish Hatchery

The project will use staged construction with half of the bridge under construction at any given time. For each phase, the eastbound vehicular traffic will be detoured, and the westbound traffic will remain in the single lane provided on SR 2010. The westbound direction will remain open to provide access for emergency vehicles headed to Lehigh Valley Hospital. The eastbound detour will utilize PA Routes 29, I-78, SR 2005 (Lehigh Street), and SR 2007 (Oxford Drive). This detour route will be approximately 4.5 miles in length. Pedestrians will be detoured throughout construction.

Please remember to complete a questionnaire. If you have any questions concerning this project, please do not hesitate to contact PennDOT District 5-0, Consultant Project Manager, Michael McGuire, PE at 610.783.3825 or email at c-micmcgui@pa.gov
 

Contact Information

Michael  McGuire, PE

PennDOT Consultant Project Manger

610-783-3825

c-micmcgui@pa.gov

Ronald J. Young, Jr., M.P.A.

Press Officer

610-871-4555

ronyoung@pa.gov

 

Accessibility

The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Manager listed above.

Title VI

Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.