Southeast Community Information

Bishop Tube

This page was last updated on December 18, 2025

Site Facts

Location:
Malin Road, south of U.S. Route 30, East Whiteland Township, Chester County

Hazardous Sites Cleanup Program (HSCA) Site Since:
1999

Contaminants of Concern: 
Trichloroethene (TCE) its breakdown products, per- and polyfluoroalkyl substances (PFAS), certain heavy metals, and other contaminants have been detected in soil, surface water, groundwater and/or indoor air at the Site

Historical Use:
Stainless steel tubes were manufactured from the 1950’s until 1999

Previous Property Owners and Operators:
Johnson Matthey Inc. (previously known as J. Bishop, Matthey Bishop) , Whittaker Corporation, Christiana Metals Corporation, Alloy Steel Corporation, Marcegaglia USA, Central & Western Chester County Industrial Development Authority

Current Property Owner:
Constitution Drive Partners L.P. (CDP)

Listing:
On September 11, 2010 DEP facilitated the future
Remedial Response action(s) as defined in HSCA by placing the Site on Pennsylvania’s Priority List of Hazardous Sites for Remedial Response (“PAPL”)

DEP Project Officer:
Dustin Armstrong, 484-250-5723 or darmstrong@pa.gov

What's New

In August 2025, DEP tasked a contractor, Groundwater & Environmental Services, Inc (GES) to perform the data gap pre-design investigation. See the Pre-Design Investigations Section below for links to the plans associated with this work. As noted in the work plan, the investigation activities will include:

  • Site preparation activities including some tree and brush removal to allow for access by soil boring and well drilling equipment. Work is scheduled for Monday, December 22 and Tuesday, December 23.
  • Soil borings collected on the Bishop Tube property. The samples will be evaluated for PFAS, fluoride, volatile organic compounds, and inorganics. Work will likely begin in January 2026 subject to weather conditions and/or contractor availability.
  • The installation of a monitoring well in the northeast corner of the Bishop Tube property, accessed from the west end of Village Way. Work will likely begin in January 2026 subject to weather conditions and/or contractor availability.
  • Site groundwater monitoring wells and surface water samples will be analyzed for all contaminants of concern, including PFAS. Sampling will follow the well installation activities.

As we conduct these investigation activities, you may see DEP personnel and DEP contractors accessing the Bishop Tube property from both Malin Road and Village Way.  If you have any questions or concerns during our activities, please do not hesitate to contact us directly using the contact information on this web page.

Background

  • The Bishop Tube HSCA Site consists of areas of groundwater, soil, and surface water contamination. Groundwater contamination at the Site flows beneath certain properties located along South Malin Road, Lancaster Avenue (US Rt. 30), Conestoga Road (PA Rt. 401), Morehall Road (PA Rt. 29), and Village Way.

  • The known sources of the contaminated groundwater and surface water and areas of contaminated soil are located on the former Bishop Tube property ("Source Property"), currently owned by CDP.

  • DEP's responsibility under the Hazardous Sites Cleanup Act ("HSCA") is to select a remedy that is protective of human health and the environment and complies with all statutory and regulatory requirements.
     

What is being done to clean up the Site?

  • In September 2022, DEP selected a remedial response action to address soil, groundwater, surface water, and a residential drinking water supply.

  • DEP plans to remediate the Site to a combination of residential Act 2 standards, based on the anticipated end use of the Source Property. DEP divided the Site into three operable units ("OUs"). The selected remedy includes
    • Operable Unit 1 (OU1) - In Situ Chemical Oxidation and/or In Situ Chemical Reduction (PDF) ("ISCO/ISCR"), coupled with soil mixing to address unsaturated and saturated soils impacted by Site contaminants of concern ("COCs");
    • Operable Unit 2 (OU2) - In situ injection of ISCO, ISCR or bioremediation amendments in the two primary chlorinated solvent source areas to address contaminated groundwater with engineering, and/or institutional controls, and long-term monitoring; and
    • Operable Unit 3 (OU3) connection of the residence with an impacted domestic well to the existing public water line.
  • The total estimated present value cost of the final remedial response action is $8.1M.
  • The impacted residential property was connected to a public waterline in June 2023.


What's Next

  • Following the completion of all pre-design investigation activities, a pre-design investigation report will be prepared and posted on this website, and DEP will schedule a public meeting to discuss the results.

    Report an Environmental Health Concern

    While DEP is unaware of any confirmed environmental health issues related to the Site, some residents have expressed concerns to DEP. Pennsylvania residents with such concerns are encouraged to report environmental health concerns to the Pennsylvania Department of Health (DOH), where they will be evaluated and referred to an appropriate program area for potential investigation and follow-up. Please indicate in your message that your concern is related to the Bishop Tube Site.

    Community Outreach

    Additional Information

    • East Whiteland Township utilized a Technical Evaluation Grant (TEG) pursuant HSCA to conduct an independent technical evaluation of the proposed remedial response at the Site.

    • On August 9, 2023  (PDF) DEP communicated to East Whiteland Township on certain aspects of Constitution Drive Partners, LP. Final Land Development Submission, dated June 2023.

    The administrative record which contains the information that forms the basis and documents the selection of the response action was available for public review and comment between September 24, 2021 and January 31, 2022.

    • Bishop Tube Administrative Record (PDF) 
      *Hard copies of the Administrative Record are also available for review in DEP’s Southeast Regional Office and the East Whiteland Township Municipal Building. Due to various limitations, such as size and reproducibility, as noted on the docket, a few records will be available only electronically.

    ✓ Completed Steps,  ★ Current Step,  ● Next Steps

    ✓  Remedial Investigation/Feasibility Study (RI/FS)1/13/2021
    Remedial Response Action Proposal9/24/2021
    Public Hearing11/9/2021
    Response to Public Comments9/8/2022
    Signature of the Statement of Decision (SOD)9/12/2022
    Closing of the Administrative Record9/21/2022
    Work Plan for OU-3 (Public Waterline) Implementation1/6/2023
    Remedial Action: OU-3 (Public Waterline) Construction and ConnectionMay and June 2023
    Public MeetingSeptember 12, 2023
    Data Gap Pre-Design Investigation ActivitiesJanuary - March 2026
    Data Gap Pre-Design Investigation ReportSpring 2026
    Public MeetingSpring/Summer 2026
    Preliminary IC/EC & OU1 Remedial Design Investigation Work PlanTBD
    Remedial Design (RD) - During the Remedial Design phase, the plans for the cleanup method are carefully designed. The Remedial Design is based on the cleanup method described in the SOD.TBD
    Remedial Action (RA) - The Remedial Action (RA) starts the actual cleanup at a site.TBD
    Operation and Maintenance (O&M) ActivitiesTBD

    Community Updates

    To subscribe to updates, please send an email to: RA-EP-SEROECB@pa.gov

    Please indicate in the subject line or text of the email that you’d like to receive updates related to the Bishop Tube HSCA Site.

    Additional Contact Information 

    To schedule an appointment to review files associated with the Bishop Tube site and project, please call the Norristown Office at 484-250-5910.

    Please direct correspondence or inquiries to one of the following:

    Project Information: 
    Dustin Armstrong,
    Project Officer
    darmstrong@pa.gov & 
    RA-EP-SEROECB@pa.gov

    Christine McCarthy,
    Supervisor
    chmccarthy@pa.gov
     

    Community and Media Relations: 

    Robyn Briggs,
    Regional Communications Manager
    robbriggs@pa.gov

    Legal: 
    Adam Bram,
    Regional Counsel abram@pa.gov


    Robert E. McDivitt III,
    Assistant Counsel rmcdivitt@pa.gov

    Legislative Inquiries: 
    Lisa Strobridge, PG,
    Local Government Liaison
    lstrobridg@pa.gov