King of Prussia, PA – The Pennsylvania Department of Transportation (PennDOT) announced today that resurfacing operations are scheduled on several state highways in Philadelphia, Bucks, and Chester counties, under several projects to repair and pave more than 200 miles of state highway across the Philadelphia Region.
The work schedules and locations are:
Philadelphia
- Monday, July 31, through Friday, August 4, from 9:00 AM to 3:00 PM and 7:00 PM to 6:00 AM the following morning, a lane closure is scheduled on Frankford Avenue between Pratt Street and Girard Avenue for prepping and paving;
- Monday, July 31, through Friday, August 4, from 9:00 AM to 3:00 PM, lane closures are scheduled in both directions on U.S. 1 (Roosevelt Boulevard) between Adams Avenue and Summerdale Avenue for intersection improvements; and
- Monday, July 31, through Friday, August 4, from 9:00 AM to 3:00 PM, a lane closure is scheduled on Aramingo Avenue between York Street and Wheatsheaf Lane for prepping.
Bucks County
- Monday, July 31, through Friday, August 11, from 7:00 PM to 5:00 AM the following morning, weeknight alternating lane closures are scheduled in both directions on Route 332 (Newtown Bypass) between northbound Route 532 (Newtown Bypass) and Newtown Gate Drive/Summit Trace Road in Newtown Borough for milling and paving.
Chester County
- Sunday, July 30, from 4:00 PM to 5:00 AM the following morning, a lane closure is scheduled on Swedesford Road between Route 252 (Valley Forge Road) and West Valley Road in Tredyffrin Township for paving;
- Sunday, July 30, through Friday, August 4, from 9:00 AM to 3:00 PM and 6:00 PM to 6:00 AM the following morning, a lane closure is scheduled on Westtown Road between Old Westtown Road and the Delaware County line in Westtown, West Goshen, and Thornbury townships for casting adjustments, milling and paving;
- Monday, July 31, through Friday, August 4, from 7:00 PM to 5:00 AM the following morning, a lane closure is scheduled on Swedesford Road between Route 252 (Valley Forge Road) and West Valley Road in Tredyffrin Township for paving;
- Monday, July 31, through Friday, August 4, from 7:00 PM to 5:00 AM the following morning, alternating lane closures are scheduled in both directions on Paoli Pike between Five Points Road and Westtown Road/Garfield Avenue in West Goshen Township for milling and paving; and
- Monday, July 31, through Friday, August 4, from 9:00 AM to 3:00 PM and 7:00 PM to 5:00 AM the following morning, a lane closure is scheduled on Route 23 (Nutt Road) between Route 113 (Kimberton Road) and Route 29 (Main Street/Manavon Street) in Phoenixville for casting adjustments, milling, and paving.
Motorists are advised to allow extra time when traveling through the work areas because slowdowns will occur. All scheduled activities are weather dependent.
Currently, PennDOT is working on several resurfacing projects in the Philadelphia Region totaling $134 million. Under these projects, PennDOT is milling the existing roadway surfaces and repaving the state highways with new asphalt. The new pavement will seal the roadways and provide motorists with a smoother riding surface.
Motorists can check conditions on more than 40,000 roadway miles by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras.
For a complete list of construction projects impacting state-owned highways in Bucks, Chester, Delaware, Montgomery, and Philadelphia counties, visit the District 6 Traffic Bulletin.
Information about infrastructure in District 6, including completed work and significant projects, is available at www.penndot.pa.gov/D6Results. Find PennDOT's planned and active construction projects at www.projects.penndot.gov.
Subscribe to PennDOT District 6 news and traffic alerts at www.penndot.pa.gov/District6.
Follow PennDOT on Twitter and like the department on Facebook and Instagram.
Contact: Robyn Briggs, robbriggs@pa.gov
# # #