Montoursville, PA – Motorists are advised that a resurfacing, bridge preservation and ADA accessible sidewalk upgrade project is set to begin next week on Routes 11 (Water Street) and 147 in Northumberland Borough, Northumberland County.
Week of July 10
Beginning on Monday, July 10, 2023, the contractor, New Enterprise Stone and Lime, will begin base repairs followed by milling work on northbound Water Street in Northumberland Borough from King Street to C Street. This work will be performed between the hours of 6:30 AM to 5:00 PM Monday through Friday.
Week of July 17
The week of July 17, 2023, the contractor will begin constructing new ADA accessible sidewalks and curbs at intersections of Orange Street and Hanover Street. Work will also occur on Route 147 from South Second Street to the Bridge that spans Shamokin Creek. This work will be performed between the hours of 6:30 AM to 5:00 PM Monday through Friday.
Week of July 31
Beginning Sunday, July 30, 2023, night work begin and will be performed Sunday thru Friday, between the hours of 8:00 PM and 4:00 AM.
New Enterprise Stone and Lime is the prime contractor for this $ 2,381,802.00 resurfacing, bridge preservation, and ADA upgrade project. Once resurfacing is completed, the contractor will install pavement markings and signing upgrades throughout the project area.
This project is expected to be completed by late September, 2023, weather permitting. Motorists should be alert, slow down, watch for lane changes, and drive with caution through the work zone.
Motorists can check conditions on major roadways by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras.
511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional Twitter alerts.
Subscribe to PennDOT news and traffic alerts in Tioga, Bradford, Lycoming, Sullivan, Union, Snyder, Northumberland, Montour and Columbia counties at www.penndot.pa.gov/District3.
Information about infrastructure in District 3 including completed work and significant projects, is available at www.penndot.gov/D3Results. Find PennDOT's planned and active construction projects at www.projects.penndot.gov.
Follow PennDOT on Twitter and like the department on Facebook and Instagram.
Contact; Kim Smith, 570-368-4344 or kiasmit@pa.gov
# # #